TWINNING
ARRANGEMENT CONSULTANCY
The
Twinning Consultancy was taken up with the aim to develop the management,
planning , operation & maintenance capabilities of CMWSS Board and to ensure
that it is operated in the most efficient and cost effective manner as possible.
The work was taken up by the
consultant M/s. Compagnie Generale Des Eaux . The Twinning consultancy is in two Phases (ie) Phase I -. Diagnostic study
and Phase II –
Implementation Year I and Year II & III
Phase-I : Diagnostic
Study :
The
diagnostic study commenced in Sep 2000 and completed in March 2001.
Phase-II
: Implementation
After
the diagnostic period 25 activities were taken up for implementation during
Phase-II Year-I and 24 activities were completed
and one activity was carried over to Year 2 & 3 study. 12 activities
were further taken up for implementation during Phase II year 2&3
from Sep 2002 onwards. The
most important among them are :
Implementation of ISTP
Implementation of GIS
Implementation of
Bulk Metering
Implementation of
Pilot Metering
Study on existing Well fields and the raw water conduits
Refurbishment of Kilpauk
Water Treatment plant