|
Projects consists of the following components
i) Unfinished works from the first project
The major items of works which are included in this component are construction
of clear water pumphouse at Red hills, installing archemedian screw pumps
at Koyambedu sewage treatment works and improvements to 16 sewage pumping
stations.
ii) Clear water transmission mains
In order to have equitable distribution of water to the consumers, the
city is divided into 16 water supply zones. Each zone was proposed to be
provided with a water distribution station which are connected by clear water
transmission mains from the treatment plants. Under the Second Chennai project,
6 numbers of transmission mains viz. K.K.Nagar to Ekkattuthangal, Madhavaram
to Vyasarpadi, Porur to Kathipara, Kathipara to Pallipattu, Pallipattu to
Mylapore and Velachery to Velachery water distribution station were taken
up and completed. An additional branch transmission main from Purasawalkam
to Triplicane and Kannappar Thidal distribution station was also taken up
later and completed.
iii) Water distribution station
All the 7. Water Distribution Stations taken up under this project, viz
Patel Nagar, Kolathur, Palipattu,Vyasarpadi, Mylapore, Nandanam and Velachery
have been completed and commissioned.
iv) Local Distribution system
Under this component additional
pipelines are laid to strengthen the distribution system so that water is
made available to all consumers at a pressure of atleast 7m at their ferrule.
The work involves laying of about 660 km.of pipelines in the 11 zones (Patel
Nagar, Vyasarpadi, Kolathur, Kannappar Thidal,Choolaimedu, Mylapore,
Nandanam Valluvarkottam ,Palipattu, Ekkattuthangal, Velachery
) are completed.
v) Water conservation
Under the Leak Detection and repair, 20% of the city has been covered
in the first project under two phases. A third phase covering about 15%
of service connection was taken up and completed under this Project. Works
in the remaining 65% areas have been taken up for conducting leak detection
tests and renewal of all house service connections using MDPE pipes and replacement
of corroded and choked up mains wherever necessary. All the works contemplated
are completed.
vi) Technical Assistance
Under this component, provision has been made for the project preparation
and consultancies for the detailed design and Engineering for water distribution,
sewage collection and conveyance, sewage treatment facilities, environmental
impact assessment etc. totaling about 12 nos. All these works are completed
except 2 Nos. Presently, Twinning arrangement consultancy is in progress.
The object of this consultancy is to work along with the experts of a well
developed water utility so that improved practices are implemented and
operational efficiency of Metrowater is enhanced. Consultancy for study
on Araniar - Kosataliyar aquifer has been taken up and is in progress. This
study will assist CMWSSB to asses the water potential , abstraction and supply
of additional water to chennai.
LAST
UPDATE 22.12.2005
|