CHENNAI METROPOLITAN WATER SUPPLY AND
SEWERAGE BOARD
CHENNAI 600 002
CONTRACT NO. CMWSSB/CNT/WATER/DBOOT/001-
A/2003
REQUEST FOR PROPOSAL
FOR
Implementing a 300/200/100 mld Sea Water Desalination
Plant at Minjur, Chennai
on
Design, Build, Own, Operate and Transfer (DBOOT) basis
SUPERINTENDING ENGINEER (CONTRACTS AND
MONITORING)
CHENNAI METROPOLITAN WATER SUPPLY AND SEWERAGE BOARD
No.1 Pumping Station Road, Chintadripet,
Chennai 600 002.
(International Competitive Bidding)
Name
of work: Implementing a 300/200/100 MLD Sea Water Desalination Plant as three
options, at Minjur, Chennai on Design, Build, Own and Operate and Transfer (DBOOT)
basis on any of bidders Technology from their own funds.
Contract
No. CMWSSB/CNT/WATER/ DBOOT/001- A/2003.
The Chennai Metropolitan Water Supply &
Sewerage Board now invites sealed bids from the eligible bidders for Implementing
a 300/200/100 MLD Sea Water Desalination Plant as three options, at Minjur,
Chennai on Design, Build, Own and Operate and Transfer (DBOOT) basis on any of
bidders Technology from their own funds.
Response is solicited from Individual
Applicants/Consortia fulfilling the following criteria.
Ø
Consortia shall be with maximum of two or
three partners.
Ø
The individual applicant/consortium
members shall be a corporate
body registered under Companies Act 1956 or equivalent laws in the case of a
foreign applicant.
Ø
Experience in raising adequate finance
from Indian/International markets.
Ø
Net Worth, Turnover, Track record of the
Bidder as below:-
|
Capacity of the Plant for the bid
to be given |
Option-I (100 MLD) |
Option-II (200 MLD) |
Option-III (300 MLD) |
|
1. Technical
criteria: |
|
|
|
|
(a) Experience
of having
constructed Sea water/ Brackish Water desalination plant of minimum
capacity |
15
MLD |
30
MLD |
45
MLD |
|
(b) Experience
of having maintained for a minimum of 12 months a
Sea Water/ Brackish Water desalination plant of minimum capacity |
3MLD |
6
MLD |
9
MLD |
|
2. Financial
Criteria: |
|
|
|
|
(c) Net worth*
Rs. in Million |
1250 |
2500 |
3750 |
|
(d) Turnover * Rs. in Million |
5000 |
10000 |
15000 |
* Average
of three (3) preceding years i.e. 2000-2001, 2001-2002, 2002-2003.
Note:
(i)
The single tenderer shall satisfy the above criteria individually and in
case of joint venture any one of the joint venture partners should satisfy the
technical qualifying criteria. In
case of Consortia, the lead partner should have a net worth and turnover not
less than 50% of the value indicated above and the consortia members should
individually have net worth and turnover not less than 30% of the value
indicated above. In case of
Individual Bidder/Member of Consortia, the combined parameters of the group
companies will be taken into consideration, subject to such companies providing
a letter of comfort to this effect.
(ii)
The interested Developers are requested to bid for either or all of 100
MLD, 200 MLD, and 300 MLD capacity plants.
The decision on capacity of the plant to be set up would be made after
analysis of the bids received from interested Developers and analysis by CMWSSB
of its cost-benefit from the project. CMWSSB
shall purchase a minimum of 80% of the installed capacity on a ‘Take or Pay’
basis, with the minimum term of the Water Purchase Agreement being 25 years,
extendable thereafter on mutually agreed terms and conditions.
CMWSSB shall undertake to provide the operational power on payment of
relevant charges. The required land would be made
available by CMWSSB at Minjur.
The total period of completion is 24 months from the date of notice of
the award of the contract for all the options.
2.
Payment
Payment will be made in Indian rupees (INR) only
3.
Submission of bids
Interested eligible bidders may obtain further information from CMWSSB
and inspect the bidding document at the address given at the end, on all working
days from 10.00 hours to 17.45 hours from 29.09.2003 onwards.
A complete set of bidding documents in English may be purchased by
interested bidders on the submission of a written application to the address
given at the end and upon payment of a non refundable fee of Rs. 22,100/-
(Rupees twenty two thousand one hundred only) (inclusive of
Sales Tax and Surcharge). The
mode of payment will be through Pay Order or Demand Draft from a Scheduled Bank
in favour of Managing Director, CMWSSB payable at Chennai, Tamil Nadu, India or
by cash in the Cash counter of CMWSSB. The
document may be collected in person. The document will be sent by surface mail/courier on an extra
advance payment of Rs.1000/-(rupees one thousand only)
However, CMWSSB does not take any responsibility for the loss or delay if
any in the transmission of the document by surface mail/courier.
The period of sale of documents is from 29.09.2003 to 13.11.2003.
A Pre Bid Meeting will be held on 08.10.2003 at 11.00 hours in the office
of CMWSS Board at the address mentioned below.
The tenderer shall submit their offers in two covers (1) Technical bid
envelope and (2) Price bid envelope.
The tender documents should be submitted in a sealed cover so as to reach
the address furnished below by 15.00 hours on 14.11.2003.
All bids must be accompanied a bid security (EMD) of a value of Rs.50.00
lakhs (Rupees Fifty lakhs only) for
Option-I, Rs.100.00 Lakhs (Rupees One hundred lakhs only) for Option-II, and
Rs.150.00 Lakhs (Rupees One hundred and fifty Lakhs only) for Option-III, in the
form and manner specified in the bid document and must be delivered along with
bids. If a bidder quotes for more than one option, the initial bid security to
be deposited by him would correspond to the highest capacity quoted by him.
CMWSSB reserves the right to reject any or all the bids without assigning any
reasons thereof. All bid
clarifications, if any, will be provided by CMWSSB’s office.
Bids in Two covers viz., (1) Technical Bid envelope and (2) Price Bid
envelope must be sealed and delivered to the address given below on or before
the due date and time i.e. before 3.00 P.M. on 14.11.2003.
All bids must be accompanied with respective Bid Security (EMD) amount in
a separate sealed cover kept in the technical bid envelope.
Bids received after the given date and time shall be summarily rejected.
First cover will be opened in the presence of the bidder’s
representative who choose to attend at the address given below at 15.30 hours on
the due date indicated in the contract. After
evaluation of technical bids, the price bid envelope of the qualified bidders
will be opened in the presence of responsive bidder’s representatives who
choose to attend at the time and date to be intimated later at the address given
below:
Both national and international firms may quote.
Address: (for Information, Purchase, Delivery & Opening of bids)
SUPERINTENDING ENGINEER
CONTRACTS AND MONITORING
CMWSS BOARD
No.1 Pumping Station Road,
Chintadripet, Chennai 600 002.
Tamil Nadu, India.
Telephone :
+91 44-2852 4388
Fax
: +91
44-2853 1243
E.Mail
:
cmwssb@md2.vsnl.net.in
Web
: chennaimetrowater.tn.nic.in
MANAGING DIRECTOR
CHENNAI METROPOLITAN WATER SUPPLY AND SEWERAGE BOARD
DISCLAIMER
DISCLAIMER
1.
This Request for Proposal (RFP) is an invitation by Chennai Metropolitan
Water Supply and Sewerage Board (CMWSSB) to the interested bidders to submit
their proposals for setting up a 300/200/100 MLD Sea Water Desalination Plant as three options,
at Minjur, Chennai on Design, Build, Own and Operate and Transfer (DBOOT) basis (“the
Project”). It is not an agreement or an offer by CMWSSB to the bidders or any
other party. The purpose of
this RFP is to provide interested parties with information to assist the
formulation of their proposal. The information contained in this RFP is based on
publicly available documents.
2.
This RFP includes statements and projections, which reflect various
assumptions, which may or may not be correct. Neither CMWSSB nor its employees
or consultants make any representation or warranty as to the accuracy,
reliability or completeness of the information in this RFP. This RFP does not
purport to contain all the information each bidder may require. Each bidder
should conduct its own investigations and analysis and should check the
accuracy, reliability and completeness of the information in this RFP and obtain
independent advise from appropriate sources.
3.
Neither CMWSSB nor its employees or consultants will have any liability
to any bidder or any other person under the Law of Contract, Law of Tort, or
otherwise for any loss, expense or damage which may arise from or be incurred or
suffered in connection with any thing contained in this RFP, any matter deemed
to form the part of this RFP, and any other information supplied by or on behalf
of CMWSSB or its employees or consultants, or otherwise arising in any way from
the selection process for the Project or the award of the Project.
4.
This RFP and the information contained herein are confidential and for
use only by the person to whom it is issued. It may not be copied or distributed
by the recipient to third parties (other than in confidence to the recipient’s
professional advisor). In the event that the recipient does not continue with
its involvement in the Project in accordance with RFP the information contained
in the RFP shall not be divulged to any other party. The information contained
in the RFP must be kept confidential.
5.
CMWSSB may in its absolute discretion or at the instance of Govt. of
Tamil Nadu (GoTN), its Consultants or any bidder, but without being under any
obligation to do so, update, amend or supplement this RFP.
6.
CMWSSB reserves the right to accept or reject any or all applications or
terminate the bidding process at any stage without assigning any reason
whatsoever, without incurring any liability to the rejected bidders, and will
not be liable to compensate or reimburse to the bidders the cost or expenses
incurred or to be incurred by them in connection with the bidding process.
CMWSSB shall also not be under any obligation to inform the affected bidders of
the grounds for rejection of the application/ termination of the bidding
process.
TRANSACTION SUMMARY
TRANSACTION SUMMARY
Chennai Metropolitan Water Supply & Sewerage Board
(CMWSSB), established under the CMWSS Act 1978, looks after the supply of water
and disposal of sewage / waste water in the city of Chennai. CMWSSB is currently
undertaking several projects for augmentation of water sources to address the
projected gap between the demand and supply of water. (A brief overview of the
financials and operations of CMWSSB is furnished in the section on Demand
Estimates.) As a part of its program for bridging the water demand-supply gap,
CMWSSB proposes to augment its capacity by setting up a sea water desalination
plant.
CMWSSB has issued a Notice (Reference contract no.
CMWSSB/ CNT/WATER/DBOOT/001-A/2003) inviting experienced developers to submit
their proposals for setting up a 300/200/100 MLD Sea
Water Desalination Plant as three options, at Minjur, Chennai on Design, Build,
Own and Operate and Transfer (DBOOT) basis (“the Project”).
All bidders who fulfil the stipulated criteria are
required to submit a detailed document in accordance with the guidelines set
forth in this document, in order to satisfactorily establish their competence
and suitability for executing the Project.
The interested developers are requested to bid for
either or all of 100 MLD, 200 MLD, and 300 MLD capacity plants. The decision on
capacity of the plant to be set up would be made after analysis of the bids
received from interested developers and analysis by CMWSSB of its cost-benefit
from the project.
This RFP contains
five (5) Sections and nine (9) Appendices.
The selected bidder/ developer shall carry out and
complete the work of implementing a Sea Water Desalination Plant on DBOOT basis
at Minjur (plant capacity to be as decided by CMWSSB). The scope of work also
includes provision of required pipeline of appropriate size, pumping machinery
and construction of pump house to deliver the product water to the existing
under-ground reservoir of CMWSSB at Redhills which is about 32 kms away from the
Site.
The project shall be completed within the period
stipulated in the Bulk Water Purchase Agreement (BWPA). The completion of the
project shall be as defined in the BWPA and shall be completion of construction,
commissioning and performance tests.
CMWSSB shall purchase desalinated water equivalent to
a minimum of 80% of the installed capacity of the Plant on a ‘Take or Pay’
basis, under a Bulk Water Purchase Agreement (BWPA) to be executed between
CMWSSB and the Project Company. The term of the BWPA shall be 25 years,
extendible thereafter on mutually agreed terms and conditions. Payments under
the BWPA shall be made in Indian Rupees. The draft BWPA is given in Appendix
–9. The BWPA shall be as approved by CMWSSB.
The queries and comments of the bidders on the
proposed draft BWPA will be addressed at the pre-bid conference in accordance
with the procedure described in the section on “Procedure for Bidding”. The
changes if any will be notified through issue of an addendum as described in the
aforesaid section.
The detailed terms and conditions for the Project will be as
per the Bulk Water Purchase Agreement. The scope of work and other details
furnished in this RFP are only for the purpose of giving an outline.
For the purpose of clarification, the term
“Project Company” in this document refers to the Company/ entity
through which the Project shall be implemented by the selected developer.
The required land for the Project would be provided by
CMWSSB at Minjur on lease basis (aggregate area 60 hectares). The required land
would be provided at a nominal fee of Rs.1000/- per month. CMWSSB shall continue
to be the owner of the land. The Project Company shall enter into a site lease
agreement with CMWSSB. The site lease agreement shall follow the standard format
as approved by CMWSSB.
Necessary power for construction and operation of the
plant shall be made available at the site through the grid.
On finalisation of the plant design/ process and the
power requirement, CMWSSB would provide necessary infrastructure through TNEB[1]
at the Project site as per the lay-out to enable necessary power drawal.
The relevant charges will be borne by the developer.
As per the proposed water tariff structure, CMWSSB
shall pay the Project Company a “variable power charge”/ “energy charge”
for the power consumed in production of potable water which would be the lower
of
a)
power cost arrived at on the basis of the power
consumption in kwh/unit quoted by the developer in its price proposal, number of
water units supplied and the prevailing applicable power tariff OR
b)
power
cost computed on the basis of
the actual units billed by TNEB for water supply
In case the actual units billed by TNEB for water
supply are lower than the power consumption quoted by the developer, the
resultant savings would be shared between the Project Company and CMWSSB in
accordance with the terms spelt out in the BWPA. The detailed procedure for
payment of power charges shall be mutually worked out between CMWSSB and the
developer and, if necessary, TNEB, and will be part of the BWPA.
The proposed water tariff structure is described in
detail in the clause “Price Bid” of the section on “Evaluation of
Proposals”. The water tariff and payment of energy charge by CMWSSB will be
governed by the terms and conditions stipulated in the BWPA.
In the event of power failure, the Project Company
shall be exempted from those of its obligations under the BWPA that are affected
by the non-availability of power.
To facilitate uninterrupted supply of power to the
Plant, GoTN shall issue necessary instructions to TNEB for exempting the Plant
from power cuts/ load shedding/ according appropriate priority to the Plant for
supply of power.
GoTN, through CMWSSB, will provide all
reasonable assistance to the Sponsor for acquiring the clearances/ approvals/
permissions required for the project. An indicative list of clearances is
provided at Schedule IX of the draft BWPA. However, the final responsibility for
obtaining and maintaining these clearances shall be with the Sponsor.
The plant can be implemented using any demonstrated
technology and process for sea water desalination. However, captive power
generation is not envisaged as a apart of the project.
The Plant shall produce potable water
confirming to the prescribed water quality standards as stipulated by CMWSSB. The “product water”
specifications are laid down in Schedule III of the draft BWPA. These are based
on the standard IS no 11500 1991.
The Plant should be designed to operate with the sea
water quality available in the Bay of Bengal near the Site (source water). The
bidders shall have to identify the sea water drawl point, carry out their own
data collection exercise and analysis to assess the source water characteristics
such as temperature ranges, particle content, total dissolved solids, etc.
CMWSSB shall provide its full support to obtain the
necessary clearances so as to facilitate sea water drawal from the abstraction
point identified by the developer.
In addition to the main Plant, the developer shall be
responsible for construction and operation of systems/ accessories and any other
infrastructure facilities (including township etc.) required for successful
implementation of the Project.
The developer shall be responsible for design,
construction, operation and maintenance of the Project to meet all applicable
environmental requirements.
q
The plant should be suitable for operation in Chennai,
Tamil Nadu, India.
q
The climate of Chennai is warm with day time
temperatures being 27 deg.C to 41 deg.C during most months. The humidity is
about 70-75%.
The area being made available by CMWSSB for
the Plant, including main Plant, township and roads, is 60 acres. In the event
that more than 60 acres of land is required, CMWSSB shall endeavour to provide
the additional area depending on CMWSSB’s assessment of appropriateness of the
requirement and feasibility of providing more land.
The proposed site is located at Minjur near
Chennai. Minjur is near the northern boundary of Chennai Metropolitan Area and
is located at the sea-shore. It is approximately 50 kms. from Chennai Airport,
and approximately 26 kms. from Chennai Central Railway Station. A map of the
proposed site is attached at Appendix 8.
The product water shall be delivered to
CMWSSB at the “off-take point” at its existing under-ground reservoir at
Redhills through a pipeline of appropriate size. (The off-take point shall be as
defined and described in the BWPA..) CMWSSB will distribute the water within
Chennai city and adjoining areas through its pipeline network.
The distance of the Redhills reservoir is
about 32 kms from the Project site. The pipeline ILS alignment plan and map are
enclosed along with the BWPA. The supplying, laying and jointing of the product
water pipeline for delivery at Redhills, including construction of necessary
pumping equipment and accessories and pump house, will be a part of the scope of
work of the developer.
PROCEDURE FOR BIDDING
PROCEDURE FOR BIDDING
a.
The bidder can be a single bidder bidding on its own or on a joint
venture basis with two or three partners.
b.
To be eligible for bidding, each bidder on its own or on a joint venture
basis should satisfy the minimum eligibility criteria as laid down in the
applicable “Notice Inviting Tender” issued by CMWSSB.
Ø
Consortia shall be with maximum of two or
three partners.
Ø
The individual applicant/consortium
members shall be a corporate body registered under Companies Act 1956 or
equivalent laws in the case of a foreign applicant.
Ø
Experience in raising adequate finance
from Indian/International markets.
Ø
Net Worth, Turnover, track record of the
bidder as below:-
|
Capacity of the Plant for the bid
to be given |
Option-I (100 MLD) |
Option-II (200 MLD) |
Option-III (300 MLD) |
|
1. Technical
criteria: |
|
|
|
|
(a)
Experience of having
constructed Sea Water/ Brackish Water desalination plant of minimum
capacity |
15
MLD |
30
MLD |
45
MLD |
|
(b)
Experience of having maintained for a minimum of 12 months a
Sea Water/ Brackish Water desalination plant of minimum capacity |
3MLD |
6
MLD |
9
MLD |
|
2. Financial
Criteria: |
|
|
|
|
(c) Net worth*
Rs. in Million |
1250 |
2500 |
3750 |
|
(d) Turnover * Rs. in Million |
5000 |
10000 |
15000 |
* Average
of three (3) preceding years i.e. 2000-2001, 2001-2002, 2002-2003.
Note:
(i)
The single tenderer shall satisfy the above criteria individually and in
case joint venture any one of the joint venture partners should satisfy the
technical qualifying criteria. In
case of Consortia, the lead partner should have a net worth and turnover not
less than 50% of the value indicated above and the consortia members should
individually have net worth and turnover not less than 30% of the value
indicated above. In case of
Individual Bidder/Member of Consortia, the combined parameters of the group
companies will be taken into consideration, subject to such companies providing
a letter of comfort to this effect.
(ii)
For the evaluation, the lead
partner of the consortium should have at least 50% of the resources and other
joint venture partner should have minimum of 30% of resources. Whereas for
participation the lead partner of the consortium should have at least 51% of the
resources and the least joint venture partner should have at least 15% of the
equity. The total equity should be
100% by all the partners.
In support of fulfilling the eligibility criteria the
bidders shall furnish the required information as follows as part of the
technical bid:
a.
All details towards claim for technical experience (as per the format in
Appendix 1)
b.
Financial details including audited annual reports for the last three
financial years 2000-2001, 2001-2002, 2002-2003[2]
(as per the format in Appendix 2). If the latest audited results are not
available, provisional results certified by the Company Secretary can be
furnished.
c.
Details of bankers and insurers (Appendix 2)
d.
Write-up on experience in raising finance from Indian/ International
markets for project implementation furnishing inter alia details of projects and
amount of funds raised.
e.
Write up on experience in having established and maintained a
R.O. based Sea Water/ Brackish Water Desalination Plant during the last
10 years.
CMWSSB reserves the right to ask the bidders/ their
clients/ bankers/ insurers to provide further details/ information pertaining to
their technical and financial credentials.
Each bidder can bid either as a single bidder or as a
joint venture partner. In other words, each bidder can be a part of only one
bidding entity, whether as a sole bidder or a consortium.
The bidders can bid for either or all of 100/200/300
MLD plant configurations. In case the bidder is submitting a proposal for more
than one capacity option, the Technical Project Plan (mentioned in the contents
of the Technical Bid in the next section), shall be submitted for each capacity
option. Further, in case the bidder is submitting a proposal for more than one
capacity option, the Price Bid (details in the next section), shall be submitted
for each capacity option. The bidder can submit only one Technical Project Plan
and Price Bid for a particular capacity option.
The bidder shall bear all costs associated with the
preparation and submission of its bid and the Chennai Metropolitan Water Supply
and Sewerage Board will in no case be responsible or liable for these costs.
It shall be the responsibility of the bidder to visit
the Project site, and conduct all necessary examination and analysis pertaining
to all matters, which can in any way affect the design, construction, operation
and maintenance of the Project. It
shall be the responsibility of the bidder to carry out his own data collection
exercise and analysis to assess the characteristics of the source sea water,
which would be needed for the Project. It shall be the responsibility of the
bidder to obtain his own information on all matters which may in any way affect
his bid/ proposal. No monetory or other claims made by the bidder on the grounds
of want of knowledge of any or all of the matters related to the bid/ Project
will be entertained. The costs of
visiting the site, data collection, analysis, etc. shall be at the bidders own
expense.
7.1
The
RFP document in English may be purchased by interested bidders on the submission
of a written application to the address given at the end and upon payment of a
non-refundable fee of Rs. 22100/- (Rupees twenty two thousand and one hundred
only) or equivalent in foreign currency. The mode of payment will be through Pay Order or Demand
Draft from a Scheduled Bank in favour of Managing Director CMWSSB payable at
Chennai, Tamil Nadu, India, or by cash at the Cash counter of CMWSSB.
7.2
The RFP document may also be collected in person.
For this purpose the bidder shall send along with the application a
letter authorizing his representative to collect the RFP document personally
upon payment of the cost as specified above. The document will be sent by
surface mail/ courier on an extra advance payment of Rs.1000/- (Rupees one
thousand only). However, CMWSSB does not take any responsibility for the loss or
delay if any in the transmission of the document by surface mail/ courier.
7.3
The application for obtaining RFP document, as well as all
correspondence/ communication in connection with the RFP document, shall be made
to:
The Superintending Engineer
(Contracts
& Monitoring)
Chennai
Metropolitan Water Supply & Sewerage Board
No.1,
Pumping Station Road
Chintadripet
Chennai
600 002
Tamil
Nadu (India)
Tel
Nos: 044 2852 4388
Fax
No: 044 2853 1243
e-mail:
cmwssb@md2.vsnl.net.in
web-site
for information: www.tn.gov.in
All
correspondence/ communication by the bidders to CMWSSB should be in writing by
way of a letter/ fax. The fax copies must always be backed up by the actual
letters.
7.4
The Board does not accept responsibility either for delays in receipt of
completed bids or any delay
experienced by the applicant in receiving the bid document including loss of
document in transit. Extension of
the date and time for receipt of the completed bids/ proposals will not be made
on account of any such delays.
7.5
The RFP document can be purchased from the Office of the Superintending
Engineer (Contracts & Monitoring) at the above address between 29.09.2003 to
13.11.2003 on all working days of the Board between 10.00 hours to 17.45 hours.
The RFP document is
not transferable under any circumstances. The bids shall be accepted only from
those bidders in whose name the RFP document has been issued.
The bidder must
acknowledge the receipt of the RFP by filling out and sending to CMWSSB the form
attached at Appendix 3.
Any discrepancy detected by the bidder shall be
immediately intimated to the Superintending Engineer (Contracts &
Monitoring) at the address specified above.
Any adjustment or assumption by the bidder without such a verification
shall be at his own risk and expense.
In the event of any discrepancy between the RFP
documents and the Project Agreements such as the BWPA, the documents shall be
considered in the following priority for resolving any matter that may arise:
q
First priority: BWPA
q
Second Priority: RFP document
In general, no answer will be given to bidders in
reply to an oral question. CMWSSB shall reply to the queries of the bidders at
its discretion. Any information given to the bidders by means of the RFP
document (including any addenda) shall not be used by the bidders as the basis
of any claim or demand against the Board.
13.1.
The bidder or his authorised representative is invited
to attend a pre-bid meeting which will take place at Chennai Metropolitan Water
Supply & Sewerage Board, No.1, Pumping Station Road, Chennai. 600 002 on
08.10.2003 at 11.00a.m.
13.2.
The bidder must preferably communicate his intention
of attending the pre-bid meeting to CMWSSB in writing through letter or by fax
(to be backed up by a letter).
13.3.
The purpose of the pre-bid meeting will be to clarify
issues and to answer questions on any matter that may be raised at that stage
pertaining to the bid. Apart from
the pre-bid meeting the Board may entertain further questions from the bidders
only if they are submitted at least twenty days before the due date of
submission of the bid. The bidder must preferably submit the questions in
writing or by fax to reach the Board not later than three (3) days before the
pre-bid meeting. All queries/ issues raised by the bidders at the pre-bid
meeting will have to be backed up in writing by the respective bidders, if not
before the meeting then subsequent to it.
13.4.
The text of the questions raised by the bidders/
considered by CMWSSB, and the responses given as a result of the pre-bid
meeting, shall be communicated by the Board to all bidders. Any
modifications/additions/deletions to the RFP document including the Project
Agreements such as the BWPA shall be communicated by the Board exclusively
through the issue of an addendum and not through the minutes of the pre-bid
meeting.
CMWSSB shall endeavour to circulate the
responses to bidders’ queries and the addendum to the RFP preferably within
thirty (30) days of the pre-bid conference.
The RFP document along with the addendums
issued (if any) (which shall be construed to be part of the RFP document) shall
be the basis for bidding.
13.5.
Non-attendance at the pre-bid meeting will not be a
cause for disqualification of a bidder.
14.1.
In addition to the addendum issued after the pre-bid
meeting, before the deadline for submission of bids, the Board may modify the
RFP document by issuing addenda.
14.2.
Any addendum thus issued shall be part of the RFP
document and shall be communicated in writing or by fax to all the bidders.
Bidders shall acknowledge receipt of each addendum by fax and letter to
the Board.
14.3
Adequate time for submission of bids will be ensured
when such addendum is issued.
15.1
Bidders are advised to go through the RFP document in
full detail and understand all the provisions and stipulations contained therein
before submitting the bids.
15.2
The bid shall be submitted exactly as per the
procedures and requirements stipulated herein.
15.3
The bid must be submitted so as to be received within
the stipulated date and time mentioned herein.
15.4
Bids submitted by telex, cable or fax will not be
accepted and will be summarily rejected.
16.1
The bid shall be accompanied by an Initial Bid
Security for a value of Rs. 50 lakhs for 100 MLD plant, Rs. 100 lakhs for 200
MLD plant and Rs. 150 lakhs for 300 MLD plant. If a bidder quotes for more than
one option, the Initial Bid Security to be deposited by him would correspond to
the highest capacity option quoted by them. No exemption of bid security will be
permitted for any bidder even for any Govt. body of any country.
16.2
After the opening of the Technical Bid, the
technically qualified bidders, whose price bid is proposed to be opened by
CMWSSB, shall submit an Final Bid Security for a value of Rs.
250 lakhs for 100 MLD plant, Rs. 500
lakhs for 200 MLD plant and Rs. 750 lakhs for 300 MLD plant.
If a bidder has been technically qualified for more than one option, the
Final Bid Security to be deposited by him would correspond to the highest
capacity option.
16.3
The technically qualified bidders shall submit the
Final Bid Security within twenty (20) days of CMWSSB communicating their
technical qualification to them and instructing them to submit the Final Bid
Security.
16.4
The Initial Bid Security of the bidders who are not
technically qualified will be returned within forty-five (45) days of the
results of the technical evaluation.
16.5
The Initial Bid Security of the technically qualified
bidders will be returned after they furnish the requisite Final Bid Security.
16.6
The Final Bid Security of the successful bidder shall
be discharged after the bidder has furnished the required Development Security
and signed the Bulk Water Purchase Agreement as per the prescribed format.
16.7
The Final Bid Security of unsuccessful bidders will be
returned within forty-five (45) days of the signing of the BWPA.
16.8
Any bid submitted without the Bid Security in the form
as specified in the RFP document shall be summarily rejected.
16.9
The Initial/ Final Bid Security shall be forfeited if:
i.
The bidder withdraws his bid after bid opening and
during the bid validity period.
ii.
In case
of a successful bidder, if the bidder fails within the specified time limit to
furnish the required Development Security, or fails to execute the Bulk Water
Purchase Agreement.
iii.
In case
of technically qualified bidders, if they fail within the specified time limit
to furnish the required Final Bid Security, then their Initial Bid Security
shall be forfeited.
16.10
The form of the Initial/ Final Bid Security will be as
follows:
q
The Bid Security should be in the form of a Bank Draft
or Pay Order drawn on any Nationalised/ Scheduled Commercial Bank in favour of
the Managing Director, CMWSSB, payable at Chennai, Tamil Nadu, India.
q
The Bid Security may also be in the form of
irrevocable Bank Guarantee. The format of the Bank Guarantee shall be as per
Appendix 5. Bidders are to note
that the format of the Bank Guarantee should not be altered under any
circumstances. Bidders are advised
to strictly adhere to the format and the value to avoid disqualification.
q
The irrevocable Bank Guarantee shall be on a
non-judicial stamp paper of value not less than Rs .20/- and shall be submitted
from a Nationalised/ Scheduled Commercial Bank.
q
The validity of the Bank Guarantee/Bank Draft/Pay
order shall be for a period of six (6) months from the due date of submission of
the bid with a claim period of two (2) months thereafter.
17.1
Bids which are conditional or obscure or which contain
additions not called for,
erasures,
alterations or irregularities of any kind will not be considered.
17.2
The bidder shall fill up and sign all schedules,
tables, forms, drawings, etc., and provide all description and information, as
stipulated in this RFP document.
The bid shall be signed by a person or persons duly
authorised to sign on behalf of the bidder.
All pages of the bid where entries or amendments have been made shall be
signed by the person or persons signing the bid. The bidder shall enclose a
certified copy of the Power of Attorney authorizing the signatory or signatories
to sign the bid document. This
certification shall be from the Company Secretary or the authorized Legal
Manager of the firm.
In case of proposals from a consortium of members, the
signatures would have to be those of the authorized signatory/ signatories of
the consortium leader.
In case of a consortium of partners bidding jointly
for the project a “letter of association” shall be furnished as part of the
bid on behalf of the consortium, which shall state the following:
-
that the various members have decided to form a
consortium to bid for the Project
-
the name of the consortium leader
-
the proposed percentage equity contribution of each
member to Project
-
that each member has examined the bid document and is
in agreement with its contents
This letter should be signed by the respective
authorized signatory/ signatories of each consortium member.
It may be noted that in case of the selected bidder, a
JV Agreement outlining the roles and responsibilities of the consortium members
(if applicable) shall have to be executed and registered before the signing of
the BWPA.
20.1
Bids/proposals in sealed envelope/ package as detailed
below will be received by the Superintending Engineer (Contracts &
Monitoring) at his office up to 3.00 pm on 14.11.2003.
If the said date happens to be a holiday for the Board, the Tenders will
be received up to 3.00 pm on the next working day.
20.2
The Board may extend the due date for submission of
bids by issuing an addendum in which case all the rights and obligations of the
Board and the bidders previously subject to the original due date for submission
will then be subject to the new date for submission as extended.
21.1
The bid shall be submitted in three parts viz. Part
A (Bid Security), Part B
(Technical Bid) and Part C
(Price Bid). The contents of each part shall be as described in the
subsequent clauses. Each part shall be placed in an independent sealed envelope.
Each envelope shall be labelled as follows:
|
PART – A |
BID
SECURITY ENVELOPE |
|
Contract Reference No |
CMWSSB/CNT/WATER/
DBOOT/001 – A /2003
|
|
Project |
Implementing a Sea Water Desalination Plant at Minjur,
Chennai on Design, Build, Own, Operate and
Transfer (DBOOT) basis. |
|
Due date/ time |
14.11.2003
/ 3.00 P.M. |
|
Name of bidder |
BIDDER’S NAME TO BE INSERTED |
|
PART – B
|
TECHNICAL
BID ENVELOPE |
|
Contract Reference No
|
CMWSSB/CNT/WATER/
DBOOT/001-A /2003
|
|
Project |
Implementing a Sea Water Desalination Plant at Minjur,
Chennai on Design, Build, Own, Operate and
Transfer (DBOOT) basis. |
|
Due date/time |
14.11.2003/
3.00 P.M. |
|
Name of bidder |
BIDDER’S NAME TO BE INSERTED |
|
Plant Capacity |
---
MLD (as applicable) |
|
|
Note:
The bidder shall submit one Technical Bid for each capacity option for
which he chooses to bid. Thus, he shall submit three Technical Bid
Envelopes in case he is bidding for all three capacities. Each Technical
Bid Envelope should be marked with the plant capacity as appropriate. |
|
PART - C |
PRICE
BID ENVELOPE |
|
Contract Reference No |
CMWSSB/CNT/WATER/DBOOT/ 001-A /2003
|
|
Project |
Implementing a Sea Water Desalination Plant at Minjur,
Chennai on Design, Build, Own, Operate and
Transfer (DBOOT) basis. |
|
Due date/time |
14.11.
2003 / 3.00 P.M. |
|
Name of bidder |
BIDDER’S NAME TO BE INSERTED |
|
Plant Capacity |
---
MLD (as applicable) |
|
|
Note:
The bidder shall submit one Price Bid for each capacity option for which
he chooses to bid. Thus, he shall submit three Price Bid Envelopes in case
he is bidding for all three capacities. Each Price Bid Envelope should be
marked with the plant capacity as appropriate. |
The
envelopes containing Part A, Part B and Part C shall be placed inside an outer
envelope and shall be labelled as follows:
Implementing a Sea Water Desalination Plant at Minjur,
Chennai on Design, Build, Own, Operate and
Transfer (DBOOT) basis.
This envelope contains ---
(number of envelopes to be indicated in words and figures) independent sealed
envelopes as follows:
PART - A
:
Bid Security Envelope
PART - B
:
Technical Bid Envelope (Indicate capacities bid
for
and number of envelopes)
PART - C
:
Price Bid Envelope (Indicate capacities bid for
and
number of envelopes)
Contract Reference No:
CMWSSB/CNT/WATER/DBOOT/001- A /2003
Due Date & Time
:
14.11.2003 / 3.00 P.M.
The
package shall be addressed to:
The Superintending Engineer
(Contracts & Monitoring)
Chennai Metropolitan Water Supply
& Sewerage Board
No. 1 Pumping Station Road
Chintadripet
Chennai
600 002
India
Each envelope shall carry the name and the address of the bidder
prominently.
FORM AND EVALUATION OF PROPOSALS
1.1
Bids shall remain valid for a period of one hundred
and eighty (180) days from the due date of submission of the bid.
1.2
In exceptional circumstance, prior to expiry of the
original time limit, the Board may request bidders to extend the period of
validity for a specified additional period.
The request and the bidders’ responses shall be made in writing or by
fax (to be backed up in writing). A
bidder may refuse the request without forfeiting his Bid Security.
A bidder agreeing to the request will not be permitted to modify his bid.
However, he shall extend the validity of the Bid Security Bank Guarantee
for the period of the extension.
The Bid Security envelope shall contain the following
as per the sequence indicated below:
i)
Covering letter stating name of the bidder and
capacity options for which he is bidding
ii)
Letter of association for consortium bidders (as
mentioned in the section “Procedure for Bidding”)
iii)
The Bid Security Bank Guarantee as per Appendix
5. The Bid Security value shall correspond to the highest capacity option
for which the bidder is bidding.
The bidder shall submit one Technical Bid for each
capacity option for which he has chosen to bid. Each Technical Bid envelope
shall be marked with the appropriate capacity as described in the preceding
section. The Technical Bid envelope shall contain the following as per the
sequence indicated below (All contents of the Technical Bid shall be submitted
in duplicate.):
i)
Declaration by the bidder that his bid is without any
technical and commercial deviations
in the format of the letter as per Appendix
4.
ii)
Certified Power of Attorney authorising a
representative or representatives of the Company to sign the bid and all
subsequent communication.
iii)
Information towards establishing technical experience
as per the Response Sheet at Appendix 1.
iv)
Information towards establishing financial capacity as
per the Response Sheet at Appendix 2.
v)
Technological Process and Plant Design, Construction,
Operation & Maintenance Plan including inter alia the following items:
(a)
Full technical description of the process and
technology adopted to be given, specifications of the equipment and materials to
be stated.
(b)
Details of other projects where similar technology has
been adopted by the bidder
(c)
Write-up on experience in raising finance from Indian/
International markets for project implementation furnishing inter alia details
of projects and amount of funds raised.
(d)
Work methodology and plan for implementing the project
including Bar Charts/ Pert Charts etc.
(e)
Plant design with drawings
(f)
Proposed abstraction area and abstraction system
(g)
Details of various systems such as the following are
to be given:
·
Sea water intake system
·
Pre-treatment system
·
Main treatment system
·
Product water post-treatment and storage system
·
Brine and sludge disposal system
·
Product water conveyance system and pumping system
(h)
Planned Operation and Maintenance procedures for the
Plant
(i)
Various performance parameters like quality of product
water, quality of sea water discharge, recovery levels etc.
(j)
Compliance with environmental norms.
(k)
Organizational plan indicating roles and
responsibilities of different departments and different consortium members (in
case of consortium)
(l)
Any other technical details
The Technical Bid envelope shall not contain any reference to
price.
The bidder shall submit one Price Bid for each
capacity option for which he has chosen to bid. Each Price Bid envelope shall be
marked with the appropriate capacity as described in the preceding section. The
envelope labelled as "Price Bid Envelope" shall contain the following
in the sequence indicated below:
i.
Covering letter
ii.
Price for desalinated water to be paid by CMWSSB
year-wise for 25 years , which shall have the following components:
a)
Water Capacity Charge
To be quoted in Rs. for each year for 25 years as per
the format at Appendix 6. This would go towards covering fixed costs such as
interest, depreciation, ROE[3]
and fixed O&M costs. The payment to the developer shall be on the basis of
plant availability, in accordance with the terms spelt out in the BWPA. There
shall be no provision for any escalation.
b)
Energy Charge
The bidder shall quote the power consumption in terms
of no of units (kWH per KL) as per the format at Appendix 6. This would go
towards covering the power consumption costs for water supplied. The payment to
the developer shall be on the basis on power consumption quoted, water units
supplied, and the prevailing applicable electricity rate, in accordance with the
terms spelt out in the BWPA.
c)
Water Variable Charge
To be quoted in terms of Rs per KL as per the format
at Appendix 6. This would go towards covering variable costs (other than power
costs) for water supplied such as variable O&M costs and consumable costs.
The payment to the developer shall be on the basis on per unit charge
quoted (base value) indexed to the Indian WPI[4],
and number of water units supplied, in accordance with the terms spelt out in
the BWPA.
The
Water Variable Charge “C” payable by CMWSSB in any billing month shall be as
follows:
C = c * q * WPIn/WPI0
Where,
|
c |
= |
water variable charge per unit quoted by developer for the applicable
year in Rs per KL |
|
q |
= |
water units supplied in that billing month in KL |
|
WPIn |
= |
Indian Wholesale Price Index prevailing on the first day of the
applicable operating year |
|
WPI0 |
= |
Indian Wholesale Price Index prevailing on the Project Commercial
Operation Date (COD) |
Any
bids received by the Board after the due date & time specified herein will
not be considered and will be returned unopened to the bidder.
6.1
Bidders may modify or withdraw their bids by giving notice in writing
before the due date of submission of the bid.
6.2
The bidder’s modification or withdrawal notice shall be prepared,
sealed, marked and delivered in accordance with the instructions given in the
section on “Procedure for Bidding”. The outer and inner envelopes should be
additionally marked MODIFICATION OF TECHNICAL BID OR MODIFICATION OF PRICE BID or WITHDRAWAL
as appropriate.
6.3
No bid may be modified after the due date of submission of the bid.
BID OPENING AND EVALUATION
Information
relating to the examination, clarification, evaluation and comparison of bids,
and recommendations for the award of contract, shall not be disclosed to bidders
or any other persons not officially concerned with such process until the
selection of the successful bidder has been announced.
Any effort by a bidder to influence the Board in the processing of bids
or award decisions may result in the rejection of his bid.
CMWSSB
will open the Bid Security and Technical Bid envelopes in the presence of the
bidders or their authorised representatives at 3:30 p.m. on 14.11.2003. In the event of the specified date of bid
opening being declared a holiday for the Board, the envelopes will be opened at
the same time on the next working day.
CMWSSB
shall evaluate the bids in a stage-wise manner described below.
To
assist the examination, evaluation and comparison of bids, the Board may, at its
discretion, ask any bidder for clarification on his bid.
The request for clarification and the response shall be in writing or by
fax (to be backed up by written communication). No change in the substance of
the bid shall be permitted.
CMWSSB
shall first open the Bid Security and Technical Bid envelopes and assess whether
the bidder fulfils the minimum qualifying criteria and whether the bids are
responsive. The Board shall assess whether the proposal is in accordance with
the guidelines stipulated in the RFP document viz. whether the Initial Bid
Security is in the required form, and whether the various appendices and other
documents and information have been submitted as required. If the bidder does
not fulfil the minimum qualifying criteria,
then that bidder shall be disqualified and its Price bid shall be
returned. Price Bids of the firm that are substantially non-responsive shall be
returned and their technical bids will not be returned.
CMWSSB shall then proceed with the technical
evaluation of those proposals which have not been rejected. CMWSSB shall assess
whether the technical design and standards are in line with its requirements.
The technical proposal should meet the requirements of CMWSSB in terms of
technological feasibility, environmental standards, capability to deliver the
required product water specifications, and other technical criteria.
During
technical evaluation, technical clarifications could be sought from the bidder
and would have to be furnished by him. The technical clarifications shall not
contain any price indication.
If
the proposal qualifies on the basic technical criteria, CMWSSB may require the
bidder to improve/ modify certain aspects of its technical design and submit
revised technical specifications/ design, along with resultant changes to the
price proposal (if any) in a separate sealed envelope.
v
Their Technical capability of delivering the required
quantity and quality of product water
v
Technical feasibility of Plant and process design
v
Adherence to various norms
v
Other relevant Technical Parameters.
Suitable evaluation framework will be developed in order to evaluate proposals based on different Technologies keeping in view the final objectives of CMWSSB.
(Third stage evaluation – evaluation of price
proposal)
CMWSSB
will inform the technically qualified bidders and instruct them to submit the
Final Bid Security as indicated in the previous section (Procedure for Bidding).
The
Board will proceed with opening of the “Price Bid” envelope of those bidders
whose Technical Bid has been accepted and who have submitted the Final Bid
Security within the stipulated time-frame.
The opening of the “Price Bid” envelope together with modifications
(if any) will be done in the presence of those bidders or their representatives
who choose to be present. The Board
will inform such bidders in advance about the acceptance of their Technical Bid
and the date and time of opening of the “Price Bid”.
If
the price proposal is not in accordance with the guidelines stipulated herein,
it may be treated as non-responsive.
During the course of evaluating the price proposals,
CMWSSB shall arrive at a decision on the capacity of the Plant based on analysis
of its cost-benefit from the Project under different capacity options.
CMWSSB shall evaluate the price bids by calculating
the levelized tariff on the basis of the different components of price for
desalinated water quoted by the bidder using the assumptions outlined in this
section. The price proposals for any capacity shall be compared, for the purpose
of ranking, with price proposals of that capacity only. The bidder(s) with the
lowest levelised tariff (L1 bidder) shall be ranked number.
CMWSSB shall obtain approval from its Board of
Directors for the three top-most bidders as per ranking
(L1, L2 and L3).
The levelized tariff shall be calculated on the basis
of the different components of price for desalinated water using the assumptions
as outlined in this section and detailed in Appendix 7.
The total water charge for each year shall be
calculated on the basis of the different components in the following manner:
a)
Water Capacity Charge
Quoted in Rs. for each year for 25 years. (The actual
payment to the developer shall be on the basis of Plant availability, in
accordance with the terms spelt out in the BWPA.) For the purpose of evaluation,
the Water Capacity Charge quoted for each year shall be divided by the number of
water units corresponding to 80% of Plant capacity to obtain the per unit Water
Capacity Charge in terms of Rs. per KL (=”a”). No escalation shall be taken.
b)
Variable Energy Charge
Quoted in terms of no of units (kwh) of power consumed
per KL of water supplied. (The actual payment to the developer shall be on the
basis on power consumption quoted, water units supplied, and the prevailing
applicable electricity rate.) For the purpose of proposal evaluation, the per
unit power charge for each year (=”b”) shall be calculated on the basis of
power consumption factor quoted, and the base electricity rate escalated at the
power tariff growth rate (given below).
c)
Water Variable Charge
To be quoted in terms of Rs per KL. (The actual
payment to the developer shall be on the basis on per unit charge quoted (base
value) indexed to WPI, and number of water units supplied.) For the purpose of
proposal evaluation, the per unit charge for each year (=”c”) shall be
calculated on the basis of the per unit charge quoted (base value) escalated at
the Inflation Rate (see below).
The total water charge (tariff) for each year shall be
t = a+b+c.
The levelized tariff shall be calculated using the
following formula:
25
S ti (1+d) -i
i=1
T = ------------------
25
S (1+d)-i
i=1
where
d
= discount rate
i
= ith operating year.
t i = tariff for the ith
year
T
= levellised tariff
ASSUMPTIONS FOR PRICE PROPOSAL EVALUATION
(The
economic assumptions indicated hereunder are solely for the purpose of
evaluation by CMWSSB. Bidders shall not be granted any protection for any
differentials arising out of actual parameters/ assumptions used by them
vis-a-vis those stated hereunder.)
|
S.N. |
Economic Parameter |
Rate |
Remark |
|
a)
|
Inflation Rate |
4% per annum |
Will be used for escalating the variable component
(water variable charge). |
|
b)
|
Discount Rate |
12% |
Will be used for arriving at the levelised tariff. |
|
c)
|
Base electricity rate |
Rs. 3.6 per kwh |
Will be used for calculating the power charge. |
|
d)
|
Power tariff growth rate |
4% |
Will be used for calculating the power charge. |
11.1.
The prices quoted by the bidders will be checked by
the Board for any arithmetic errors. Errors
will be corrected by the Board as follows:
a.
where there is a discrepancy between the figures and
words, the words shall be considered.
b.
a discrepancy in the total shall be corrected by
considering the lower of the sum of the individual price components and the
total as quoted by the bidder.
11.2.
The price stated in the bid will be corrected by the
Board in accordance with the above procedure for the correction of errors and
shall be binding upon the bidder. If
the bidder does not accept corrected amount, the bid will be rejected, and the
EMD will be forfeited.
AWARD OF CONTRACT
12.1
The Board will issue the Letter of Intent (LoI) to the
‘L1’ bidder for the selected capacity option (the “preferred bidder”)
prior to expiry of the bid validity period by registered letter or facsimile
(fax to be confirmed by registered letter).
12.2
If the Price Bid of the ‘L1’ bidder is
significantly at variance in relation to CMWSSB’s estimates, CMWSSB may
require the bidder to produce a price analysis, to demonstrate the internal
consistency of its prices.
13.1
CMWSSB and the ‘L1’ bidder will hold discussions
towards execution of the BWPA within the stipulated time-frame. Within thirty
(30) days of the date of issue of LOI, the selected bidder will sign the BWPA as
per the prescribed format. The
bidder shall bear the cost of the stamp paper and other legal charges.
13.2
If the L1 bidder does not execute the BWPA and submit
the Development Security within the stipulated time-frame, its LoI will stand
cancelled. CMWSSB may then approach the L2 Bidder and so on.
In order to demonstrate its commitment to
complete the construction of the Project within the stipulated period, the
successful bidder shall furnish to CMWSSB a Development Security of Indian Rs.
1000 lakhs. for 100 MLD Plant, Rs. 2000 lakhs. for 200 MLD Plant and Rs. 3000
lakhs. for 300 MLD Plant, in the form of an irrevoceable Bank Guarantee in the
format prescribed in the BWPA. The Development Security shall be submitted to
the Board within 30 days from the date of signing of the BWPA.
The successful bidder will be responsible
for the payment of all taxes, charges, fees etc. in connection with the
Development Security.
Failure
of the successful bidder to comply with this requirement shall constitute
sufficient grounds for cancellation of the LOI and BWPA and forfeiture of the
Bid Security.
Upon
the successful bidder furnishing the Development Security, and upon signing of
the BWPA, the Board will promptly notify the other bidders that their bids have
been unsuccessful and will arrange to return their Bid Security.
The Development Security will be governed
by the terms stipulated in the BWPA. 50% of the Development Security will be
released after 50% of the Project cost has been incurred as certified by the
Auditors. The balance will be released to the developer after the Project
reaches commercial operation on or before the date agreed upon in the BWPA, and
the Project achieves the performance parameters stipulated in the BWPA, and no
Liquidated Damages are payable by the developer.
CMWSSB may adjust the Liquidated Damages
payable by the Sponsor against the Development Security.
In case there are delays in achieving the
Project development and construction milestones as outlined in the BWPA, or
there are non-achievement of performance parameters as outlined in BWPA, the
Development Security will be forfeited.
PAYMENT
SECURITY FOR THE DEVELOPER AND LDs PAYABLE FOR NON-
The payment security structure for the developer will
be in accordance with the terms of the BWPA.
The following payment security is proposed for the
Project developer:
q
Escrow of identified receivables. The format of the
Escrow Agreement will be circulated at a later date.
q
Letter of Credit equivalent to 3 (three) times the
monthly Total Water Charges payable. For the purpose of arriving at the LC
amount, the monthly Total Water Charges will be calculated in the following
manner:
q
For the first twelve months after Commercial Operation
Date (COD), based on an estimate of the monthly Total Water Charges at Water
Minimum Off-take[5]
for the next succeeding month.
q
For the subsequent period, this amount will be
ü
average monthly Total Water Charges for the
immediately preceding 3 (three) months OR
ü
average monthly Total Water Charges for the
immediately preceding twelve (12) months, whichever is higher.
The LC amount will be re-calculated on a monthly basis
in the first-twelve-month-period following the COD. It will be re-calculated
once every twelve months thereafter.
Provided that while estimating the monthly Total Water
Charges for calculating the LC amount as stated above, the Variable Power
Charge, which is a component of the Total Water Charge, shall be adjusted for
any revision in power tariff implemented/ announced by the concerned electricity
supplier.
CMWSS Board is an autonomous body having independent
powers for handling its financial requirements. However CMWSS Board will meet
the commitment towards making payment to the Developer for this Project. As
such, GoTN support is not envisaged
for this Project.
If the COD for the Project is not achieved by the
stipulated date, the Company shall pay to CMWSSB liquidated damages for the delay in COD as follows.
|
Total LD for delay |
= |
(IC
x D x PD ) |
|
Where, |
|
|
|
IC |
: |
Intended Capacity of the Facility (as defined in the
BWPA and shall depend pn whether selected capacity of the plant is
100/200/300 MLD) |
|
D |
: |
the number of days of delay in achieving COD |
|
PD |
: |
Rs 10,000.00 (Rupees ten thousand) per MLD per day |
If the quality of the product water doesn’t meet the
“desirable limit” norms as given in the BWPA, the liquidated damages payable
by the Company to CMWSSB shall be as follows:
|
Liquidated
damages payable |
= |
CC
x LD x D x W |
|
CC |
: |
Contracted
Capacity |
|
LD |
: |
Rs
2000 (Rupees two thousand) per MLD per day |
|
D |
: |
the
number of days between the date of receipt of “below desirable
quality” certificate till date of restoration of desirable quality |
|
W |
: |
(D/7),
rounded off to the nearest integer at the upper range |
If the quality of the product water doesn’t meet the “permissible
limit” norms as given in the BWPA, CMWSSB shall not off-take any water till
the quality is restored. Such an event shall be treated as “failure to
supply” and the corresponding liquidated damages shall be payable.
Failure of the Company to meet the requirement of CMWSSB in providing
product water up to the minimum water off-take/ take-or-pay level, would lead to
payment of liquidated damages to CMWSSB, as follows:
|
Liquidated damages payable |
= |
WC x LD |
|
WC |
: |
total
Water Variable Charges that would have been payable by CMWSSB to the
Company for the supply of water requested by CMWSSB up to the “Water
Minimum Off-take” |
|
LD |
: |
200% |
Failure of the Company in providing product water to meet the
requirement of CMWSSB over and above up to the minimum water off-take/
take-or-pay level, would lead to payment of liquidated damages to CMWSSB, as
follows:
|
= |
WC x LD |
|
|
WC |
: |
total
Water Variable Charges that would have been payable by CMWSSB to the
Company for the supply of water requested by CMWSSB over and above the
“Water Minimum Off-take” |
|
LD |
: |
150% |
Provided that no such liquidated damages shall be payable if CMWSSB’s
required supply of water corresponds to more than the Contracted Capacity of the
Plant.
DEMAND ASSESSMENT
Demand Assessment
Chennai Metropolitan Water Supply and Sewerage Board
was established on 01.08.1978, by an Act of the Tamil Nadu Legislature to
address to the issues pertaining to water supply and sanitation in Chennai city
in a holistic manner.
CMWSSB's role is to provide adequate supply of good
quality water (along with safe disposal of sewerage/ waste water) to the
citizens of Chennai at a reasonable price and through an environment-friendly
system.
CMWSSB performs the following functions with respect
to water supply and sewerage services in the Chennai Metropolitan Area[6]:[A1]
·
Undertaking planned development to meet immediate and
long-term demand
·
Ensuring efficient operation & maintenance and
regulation
At present it serves a population of about 60 lakhs
mostly in the Chennai city area.
The present category-wise supply in Chennai
Metropolitan Area by CMWSSB is as follows:
|
Water quantity in MLD |
FY 2002 |
FY 2003 |
|
Metered
supply |
|
|
|
Chennai City |
|
|
|
Domestic |
12.28 |
32.61 |
|
Commercial |
5.44 |
10.37 |
|
Govt. Institutions |
6.03 |
6.77 |
|
Municipal bulk |
4.87 |
4.29 |
|
39.38 |
42.92 |
|
|
Sub-total (Metered supply in Chennai City) |
68.00 |
96.96 |
|
Adjacent urban areas |
|
3.91 |
Un-metered
supply
|
|
|
|
Domestic |
101.23 |
205.05 |
|
Non-domestic* |
15.75 |
16.49 |
|
Supply through tankers, domestic PSPs |
0.59 |
0.44 |
|
Sub-total (Un-metered supply) |
117.57 |
221.98 |
Total
|
185.57 |
322.85 |
*
including Commercial, Partly Comm., Govt Institutions and Industries
Thus, the total water supplied by CMWSSB in Chennai Metropolitan Area is estimated to be in the range of 200 to 300 MLD at present.
The Balance Sheet of CMWSSB for FY 2002 and FY 2003 is
as follows:
|
Rs crores |
FY 2002 |
FY 2003 |
|
Contributions |
264.21 |
306.52 |
|
Govt Grants |
304.82 |
351.25 |
|
Long Term Borrowings |
919.88 |
903.71 |
|
Deferred Credits & Surplus |
155.11 |
170.14 |
|
Current Liabilities |
352.59 |
414.17 |
|
Accumulated Surplus |
157.89 |
165.48 |
|
TOTAL |
2154.53 |
2311.27 |
|
Fixed Assets |
1702.28 |
1858.46 |
|
Current Assets, Loans &
Advances |
452.25 |
452.81 |
|
TOTAL |
2154.53 |
2311.27 |
The systems and operations of CMWSSB have been financed by Government contributions and grants, along with borrowings from Banks and Indian and Foreign Financial Institutions.
The Income and Expenditure Statement of CMWSSB for FY
2002 and FY 2003 is as follows:
|
Rs crores |
FY 2002 |
FY 2003 |
|
|||
|
|
Sale of Water |
126.63 |
146.68 |
|||
|
|
Grants & Subsidies -
drought |
75.00 |
15.45 |
|||
|
|
Water Tax & Sewerage Tax |
56.78 |
57.55 |
|||
|
|
Other Income |
25.07 |
30.50 |
|||
|
|
TOTAL |
283.51 |
250.18 |
|||
|
|
|
|
|
|||
|
|
Operating & Maintenance
Expenditure |
30.77 |
48.71 |
|||
|
|
Payments & Provision to
Employees |
50.64 |
53.47 |
|||
|
|
Office Administrative Expenses |
2.51 |
2.86 |
|||
|
|
Prior Period Adjustment |
4.99 |
3.55 |
|||
|
|
Water Lorry Hire Charges |
7.39 |
9.27 |
|||
|
|
Drought Expenditure |
82.69 |
8.02 |
|||
|
|
Depreciation |
44.20 |
48.73 |
|||
|
|
Debt Service Chrages |
56.15 |
66.85 |
|||
|
|
Provision for Doubtful Debts |
2.67 |
1.14 |
|||
|
|
TOTAL |
282.01 |
242.60 |
|||
|
|
Excess of Income Over
Expenditure |
1.50 |
7.58 |
|||
The profitability was stressed in FY 2002 owing to drought-related expenditure. However, the situation has improved in FY 2003, with increase in level of supply from 185 MLD to 322 MLD, and improvement in water sales revenues to Rs. 146 cr.
The
sources of water supply are as follows:
The drinking water needs of the Chennai area are met
through a combination of sources. The main sources of supply are:
·
Surface water stored in the lakes/ reservoirs at
Poondi, Cholavaram and Redhills (combined total capacity of 7412 mcft)
·
Ground water from the six well-fields viz. Poondi,
Tamaraipakkam, Flood Plains, Kannigaiper, Panjettty and Minjur
With
the primary water sources, the water supply level was maintained at about 290
MLD in the period before September 1996 (translating to about 70 lpcd[7]).
Additional water supply was obtained from Andhra Pradesh in September 1996,
taking the total water supply to about 480 MLD (100 lpcd).
A
water scarcity situation prevailed in Chennai in the recent past (starting from
around 1999-2000) because of rainfall shortage. CMWSSB had to adopt contingency
relief measures such as identification of new sources like agricultural
well-fields and water transportation through lorries.
CMWSSB has continued to identify new water sources, to
tackle water scarcity and to augment its main supply sources. Some of these are
mentioned below:
·
Kandaleru reservoir in Andhra Pradesh
·
Chembarambakkam tank
·
Porur tank and Rettai Eri
·
Agricultural wells
It is expected that the water requirement for Chennai
Metropolitan area would be about 1980 MLD in year 2021. Even after taking into
account the full entitlement of about 930 MLD from Andhra Pradesh, and also
various other sources, the estimated shortfall would be about 600 MLD.
CMWSSB is undertaking a number of projects to meet the
projected water requirements. As per CMWSSB’s estimates, the demand-supply
scenario is projected as follows:
Year (all in
MLD )
|
2004 |
2005 |
2006 |
2007 |
2008 |
|
Total Water Demand for Chennai City, AUAs[8]
and DUAs |
1445 |
1472 |
1499 |
1526 |
1553 |
|
Availability from sources |
|||||
|
Existing Ground water |
67 |
67 |
67 |
67 |
67 |
|
Existing Surface water |
229 |
229 |
229 |
229 |
229 |
|
De-salined water |
0 |
0 |
123 |
246 |
246 |
|
Other new projects |
0 |
490 |
580 |
620 |
890 |
|
Supply |
296 |
786 |
999 |
1162 |
1432 |
Gap
|
1149 |
686 |
500 |
364 |
121 |
It can be seen from above that a significant demand potential is expected by CMWSSB from various consumer categories in Chennai and surrounding areas. CMWSSB expects that the total demand would be in the range of 800 MLD by FY 2005.
Various projects are being undertaken by CMWSSB towards bridging the water demand-supply gap. CMWSSB is proposing various measures as a part of its comprehensive “water management strategy”:
q
Reduction of losses in the distribution system through
the “leak detection and rectification”. programme which aims to reduce the
distribution losses from about 23% to about 5%
q
Identification of additional water sources
q
Ground water conservation and recharging (Tamil Nadu
is the second state after Gujarat to enact the Rain Water Harvesting Act, and
under the Act CMWSSB is empowered to regulate ground water extraction in the
notified area.)
q
Waste water reuse
The broad break-up of sources of existing water supply is as follows:
|
MLD |
FY 2002 |
FY 2003 |
|
Ground water |
93.32 |
66.62 |
|
Surface water |
92.23 |
256.33 |
|
Total |
185.55 |
322.95 |
The following projects/ programmes are proposed for
water supply capacity augmentation:
Desalination
Plants
CMWSSB is exploring the application of desalination technology for supply of water. As a part of this programme a beginning has been made through two Reverse Osmosis Plants one at Ayodhya kuppam and another at Kasimedu kuppam in Royapuram. These Reverse Osmosis Plants are of 0.1 MLD capacity each and their technology is used for treating brackish water and supply of good quality water to the people.
The proposed sea-water desalination project is expected to be the next important stage in this programme.
Chennai
Water Supply Augmentation Project - I
The Chennai Water Supply Augmentation Project-I enables the drawal of water from Veeranam Lake and the distribution of about 180 million litres daily of treated water to the city. This project would be executed within two years. The estimated cost of the project is Rs. 720.00 crores (as approved in 2001). The project is proposed to be funded partly by the Government and partly by the National Financial Institutions. The contracts have been awarded and the works are in progress.
Chennai
Water Supply Augmentation Project - II
The Chennai Water Supply Augmentation Project II aims
at the construction of checkdams, percolation tanks, etc., to prevent rain water
running off into the sea and to store surplus water in Koratalaiyar and Palar
rivers. Detailed proposals are
under preparation and CMWSSB would approach Financial Institutions for funding
the project. This project will include:
q
Construction of Checkdams across rivers Koratalaiyar
and Palar rivers
q
Augmentation of storage capacity in Redhills
reservoir, Madhavaram Lake, Korattur Lake, Ambattur Lake and Rettai Eri.
CMWSSB is also preparing a Master Plan for supplying water to the Adjacent Urban Areas (AUAs) of Chennai.
CMWSSB is implementing the Master Plan for Water Supply & Sewerage which envisages the following goals:
q
Optimum usage of existing infrastructure and creation
of additional infrastructure to draw, treat and distribute additional water
flows contemplated from various projects
q
Zonal distribution of water supply and creation of 16
water distribution zones to cater to the ultimate demand in year 2021: The work
involves construction of additional water distribution stations, strengthening
of the distribution system, and laying of feeder mains and pipelines (involving
laying of transmission mains for conveying treated water from the treatment
plants at Redhills and Kilpauk to all the 16 water distribution stations, which
is significantly complete).
Phase 1 of the Master Plan works has been completed. The remaining works are under progress with World Bank assistance under the Second Chennai Project and are scheduled to be completed by 2003-04. The Second Chennai Project also envisages substantial additions in number of water connections.
Thus, CMWSSB has substantially enhanced and upgraded its distribution infrastructure with a view to take care of water distribution needs in the city till 2021.
CMWSSB is in the process of identifying the augmentation (if any) that would be required to distribute the water from the proposed desalination plant. The water from the desalination project will be conveyed to the Redhills reservoir from where it will be distributed to various consumer categories in the Chennai Metropolitan Area through CMWSSB’s network.
The category-wise water revenues for metered consumers, and per unit realizations for water, are as follows:
|
For Metered supply |
FY 2002 Water revenues in Rs. Lacs |
FY 2003 Water revenues in Rs. lacs |
FY 2002 Average
water tariff in Rs./KL |
FY 2003 Average water tariff in Rs./KL |
|
Chennai city |
|
|
|
|
|
Domestic |
672.28 |
993.76 |
8.00 |
8.00 |
|
Commercial |
604.26 |
1189.94 |
35.00 |
35.00 |
|
Partly-Commercial |
125.19 |
134.52 |
15.00 |
15.00 |
|
Municipal bulk |
88.88 |
149.77 |
5.00 |
5.00 |
|
Govt. Institutions |
440.23 |
518.35 |
20.00 |
20.00 |
|
Industries |
5604.85 |
6507.03 |
40.00 |
40.00 |
|
Sub-total – Metered Supply in Chennai city |
7535.71 |
9493.37 |
30.00 (Average) |
31.00 (Average) |
The water revenues from un-metered consumers are as
follows:
|
For
Un-metered supply |
FY 2002 Water revenues in Rs. Lacs |
FY 2003 Water revenues in Rs. lacs |
|
|
|
|
|
Domestic |
1774.02 |
1949.89 |
|
Non-domestic |
940.82 |
1074.68 |
|
Supply through tankers |
974.49* |
700.52 |
|
Sewerage Revenue |
1439.27 |
1449.27 |
|
Sub-total – Un-metered Supply |
5128.60 |
5174.36 |
·
due to drought and reduced water supply through pipe line, higher sale
water through tankers
The total revenues of CMWSSB from metered and un-metered consumers in FY 2003 and FY 2002 were Rs. 146 crore and Rs 127 crore respectively.
The projected water tariff for various consumer
categories is as follows:
|
Consumer
category |
FY2003 |
2004-05 |
2005-06 |
2006-07 |
2007-08 |
2008-09 |
2009-10 |
|
Rupees
per KL of water |
|
|
|
|
|
|
|
|
Metered
Consumers |
|||||||
|
Domestic |
8.00
|
9.60
|
9.60
|
10.56
|
10.56
|
10.56
|
10.56
|
|
Commercial |
35.00
|
42.00
|
42.00
|
46.20
|
46.20
|
46.20
|
46.20
|
|
Partly.
Comml. |
15.00
|
18.00
|
18.00
|
19.80
|
19.80
|
19.80
|
19.80
|
|
Govt.
Instns. |
30.00
|
36.00
|
36.00
|
39.60
|
39.60
|
39.60
|
39.60
|
|
Municipal
Bulk |
7.00
|
8.40
|
8.40
|
9.24
|
9.24
|
9.24
|
9.24
|
|
Industries |
60.00
|
66.00
|
66.00
|
72.60
|
72.60
|
72.60
|
72.60
|
|
AUA |
7.00
|
8.40
|
8.40
|
9.24
|
9.24
|
9.24
|
9.24
|
18.
Unmetered Supplies - Rupees per month per connection
|
|||||||
|
Domestic |
50.00
|
150.00
|
150.00
|
165.00
|
165.00
|
165.00
|
165.00
|