I. DIRECTORS OF THE BOARD

Chairman

Thiru Ko.Si.Mani,
Hon’ble Minister for Rural Development
and Local Administration,
1.4.99 to 31.3.2000

Managing Director

Thiru C.P.Singh,IAS,
1.4.99 to 31.3.2000

Executive Director

Thiru Rama Mohana Rao,IAS
1.4.99 to 10.6.99
Thiru Jasbir Singh Bajaj,IAS
14.6.99 to 31.3.2000

Finance Director

Thiru S.Jayaraman, IA & AS,
1.4.99 to 31.3.2000

Engineering Director

Thiru R.M.Gandhi,
1.4.99 to 31.3.2000

Ex-Officio Directors

Secretary to Government, M.A.& WS Dept.,
Tmt.S.Malathi,IAS
1.4.99 to 31.3.2000
Secretary to Government Finance Department,
Thiru P.V.Rajaraman,IAS
1.4.99 to 31.3.2000
Commissioner,Corporation of Chennai,
Thiru P.Kolappan,IAS
1.4.99 to 31.10.99
Thiru Jothi Jagarajan,IAS,
1.11.99 to 31.1.2000
Dr. J.Radhakrishnan,IAS,
1.2.2000 to 31.3.2000
 Member Secretary, CMDA
Thiru Vibhu Nayar,IAS
1.4.99 to 30.9.99
Thiru Rajeev Ranjan,IAS
1.10.99 to 31.3.2000
Managing Director, TWAD Board,
Thiru K.Deenabandhu,IAS,
1.4.99 to 30.5.99
Thiru C.P.Singh, IAS
1.6.99 to 30.6.99
Thiru A.M.Kasiviswanathan,IAS
1.7.99 to 31.3.2000

 II. OBJECTIVES OF THE BOARD

  1. To promote or secure the planned development, efficient operation, maintenance and effective regulation of water supply and sewerage systems in the Chennai Metropolitan Area;
  2. to prepare long term plans to meet the future requirement of water supply and sewerage in the Chennai Metropolitan Area based on estimates of demand, surveys on availabilities, usage of water and other relevant matters and periodical evaluation, continuous monitoring of the execution and recasting the plans to meet up-to-date needs.
  3. to undertake developmental activities with a view to meet the future requirements of water supply and sewerage in the Chennai Metropolitan Area;
  4. to operate and maintain the water supply and sewerage as may be entrusted by Government by notification to the Board;
  5. to discharge all such functions relating to water supply and Sewerage as may be entrusted by Government by notification to the Board;
  6. to undertake any other matter which is supplemental, incidental or consequential to all or any of the above functions; and
  7. to undertake such other functions as may be entrusted to the Board by or under any other law for the time being having due regard to public health, safety and convenience.
IN THE DISCHARGE OF ITS FUNCTIONS THE BOARD SHALL
  1. have due regard to public health, safety and convenience of the public;
  2. consult and collaborate with the Chennai Metropolitan Development Authority in regard to planning and undertaking development activities connected with the water Supply and sewerage systems for the Chennai Metropolitan Area and extend full assistance to and co-operate with the local authority in relation to matters connected with water supply systems or water or sewerage works or other similar works;
  3. facilitate training of personnel for and absorbing and utilising the technical know how in the Water Supply and waste water disposal sectors;
  4. Provide consultancies and managerial services and execution of any project on turn key basis or otherwise, furnishing integral service such as basic survey on preparation of detailed designs and estimates, tender procedures, execution of projects, monitoring evaluation etc. to other Urban Local Bodies in the State;
  5. control extraction, conservation and use of underground water in the Chennai metropolitan Area;
  6. prevent pollution of any water including any water source, water course or channel utilised for the purpose of the Chennai Metropolitan Area;
  7. prescribe the manner of treatment of trade effluents before discharge thereof and to regulate the discharge thereof into any sewer, canal, river or other water channels utilised for the purposes within chennai Metropolitan Area;
  8. conduct research, experiment and survey and to do all things necessary for that purpose;
  9. acquire, hold and dispose of property, necessary to carry out its operations;
  10. prepare and adopt its annual accounts and budget;
  11. determine, levy and collect taxes, rates, fees, charges, surcharges, rents and costs and expenses; and
  12. do all things necessary for the purposes of carrying out the provisions and duties assigned to it under CMWSS Act 1978 (Act 28 of 1978).
 III. A GROWTH PROFILE

Thiru Ko.Si.Mani, Chairman, CMWSS Board.

Chennai 'Metrowater' stands committed "to making a positive contribution to improve the Chennai city environment and to enhance the health and quality of life for the citizens of Chennai city by providing them with adequate supply of safe and good quality water, by collection, treatment and safe disposal of sewage at a reasonable price, and by providing customer service in a prompt and courteous manner". These are being achieved through several measures such as -

- By

    1. providing reliable and equitable water supplies in compliance with Statutory standards;
    2. collecting wastewater treating and returning it to the environment, or arranging its re-use having regard to impact and in compliance with statutory standards;
    3. using assets more efficiently to deliver the best possible service;
    4. providing timely information to stakeholders consulting and communicating with customers;
    5. developing long term strategies and actions;
    6. achieving sustainable financial self-sufficiency;
    7. maximising employee potential; and staff productivity; and
    8. monitoring performance;
 1. MASTER PLAN:

1.1. WATER SUPPLY:

To translate these higher level objectives and goals into reality, the Master Plan prepared in the year 1978 (at the time of formation of the Board), enlarged and expanded in 1991 and further updated in 1997 remains the 'Guiding Document for Planned Development'. This aims at providing ‘reliable and equitable water supply’ meeting the needs of population expected in the year 2021. For the past 3-4 years, this Master Plan has been under implementation in stages with internal resources as also with the financial assistance from Government of Tamil Nadu, Government of India, World Bank, Housing and Urban Development Corporation, Tamil Nadu Urban Finance and Infrastructure Development Corporation, etc.

      1. The Master Plan envisages optimum usage of existing infrastructure and also for carrying out the following:
    1. to draw, treat and distribute additional water flows from Krishna river., and
    2. to rectify the systemic deficiencies such as inequitable distribution, low pressure, leakage and other losses by refurbishing, rehabilitating and strengthening the distribution system.
1.1.2. To achieve the above, the concept of 'Zonal Distribution Network' has been brought in by dividing the City into 16 zones under which each zone would have a ‘self contained sub-system’ consisting of water distribution station, underground tank/overhead tank, pump house and pumpsets, transmission mains to convey treated water from the water treatment plants to the water distribution station and a net work of distribution system so as to ensure most equitable distribution in the zone.

1.1.3. Stage 1: Works for drawal of 300 mld of additional water from Redhills lake; conveyance and construction of a 300 million litres daily capacity treatment plant at Redhills; transmission mains to convey treated water from Redhills treatment plant to the water distribution stations; improvements to local water distribution systems; laying new mains in unserved areas; replacement of choked up C.I. mains, damaged AC and PVC mains, etc., were completed at a total cost of about Rs.132.00 crores between 1991-96. Consequently on receipt of Krishna Water from September 29, 1996 onwards, the city water supply could be increased from 240 MLD to 440 MLD.

1.1.4. Stage-II: Construction of 12 new water distribution stations in city and strengthening and expansion of local water distribution Net work in 11 zones viz. Choolaimedu, Kannappar Thidal, Kolathur, Vyasarpadi, Patel Nagar, Ekkattuthangal, Pallipattu, Nandanam, Mylapore, Valluvarkottam and Velachery have commenced from 1997 onwards and are programmed to be completed by 2001-2002. Works for drawal of 530 mld of raw water from Chembarambakkam tank treatment and clear water transmission mains from Chembarambakkam treatment plant to the city are programmed to be taken up from 2001 and completed by 2004.

1.1.5. Stage III: Improving existing Kilpauk water treatment plant, 4 existing water distribution stations and strengthening of local water distribution systems in the remaining 5 zones viz. Kilpauk, Anna Poonga, Southern Head Works, K.K. Nagar and Triplicane have been programmed to be taken up after 2004 and completed during 2005-2010.

1.2. SEWERAGE:

Any improvement and expansion to water supply systems can be said to be complete only when wastewater disposal system is also simultaneously improved and upgraded to handle the additional sewage flow consequent to the water augmentation. A Master Plan for upgrading the sewerage system was, accordingly, first formulated in 1978 and subsequently updated in 1991 for meeting the demand of 2021 projected population. This Master Plan is currently under implementation in stages synchronising with the improvements to water supply systems by assigning definite priority for removal of constraints in operations, extension of sewerage systems to unsewered areas where water has been provided, improvements to pumping stations and conveying mains, system-improvements to treatment plants and improvements to sewerage collection systems in that order. Strengthening of existing sewers for a length of about 143 kms; extension of sewerage system to unsewered areas involving laying of about 320 kms length of sewers and construction of 60 new pumping stations; improvements to 56 existing sewage pumping stations; and improvements and expansion of 6 sewage treatment plants are some of the important elements of the Master Plan.

1.2.1. Stage I: Constraints in about 60 locations in sewage collection systems, sewage pumping stations and sewage treatment plants have been rectified; sewers and large brick sewers rehabilitated by desilting; new sewers laid for about 6.24 km length in unsewered areas and 40 Nos. of new sewage pumping stations have been constructed. All these works at a total cost of about Rs.131.14 crores were completed in 1995.

1.2.2. Stage II: Extension of sewerage systems to unsewered areas, by laying about 68 km length of sewers, construction of 14 No. of new pumping stations, laying of pumping mains and improvements to 16 Nos. of existing large pumping stations have been taken up and are proposed to be completed by 2001. Works pertaining to the improvements required in the six existing treatment plants at a cost of about Rs.51.00 crores have also commenced and would be completed by 2001.

1.2.3. Stage III: Works relating to the strengthening of existing sewers for a length of about 65 kms, improvements to 33 existing pumping stations, strengthening of associated pumping mains for about 50 kms; and expansion of the capacity to treat an additional quantity of 264 mld of sewage totally costing about Rs.615.40 crores are proposed to be taken up and completed during 2000-2004. These works once completed would take care of the requirement of the projected population for the year 2011.

1.2.4. State IV: Remaining works to meet the requirement of 2021 population such as strengthening of existing sewers for a length of about 30.90 km., improvements to 37 existing pumping stations, strengthening of associated pumping mains for about 43 km., and expansion of capacity to treat additional quantity of 264 mld of sewage at an estimated cost of Rs.640.00 crores are proposed to be taken up and completed during 2005-2010.

2. IDENTIFICATION OF ADDITIONAL WATER SOURCES AND

CONSERVATION OF WATER:

2.1. WATER CONSERVATION MEASURES

2.1.1 Water sources availability and its adequacy to meet the demand for water needs have been the uppermost thrust area for the Board. As per the Master Plan the demand for water supply in the year 2021 would be about 2000 mld as against the availability of about 1400 mld obtainable from all existing sources including Krishna River source.

2.1.2. Conserving a commodity for future use and maintaining the current commodity usage at optimum level would always lead to savings in the quantity available. Taking cognizance, of this, the Board has evolved a "well conceived water conservation policy" which systematically embarks upon several conservation measures. Some of these include:-

    1. Leak Detection and Rectification Works
    2. Rainwater Harvesting,
    3. Control and Regulation of Indiscriminate Extraction of Ground Water
    4. Recharging of Ground Water; and
    5. Re-use of secondary treated sewage for industrial purposes.
The action plans for these measures and also the action taken status are as detailed in the following paragraphs.

2.2. LEAK DETECTION AND RECTIFICATION WORKS

2.2.1. Tackling systemic losses and reducing the 'unaccounted for water' have been high on the agenda of the Board. Under a well conceived 'Leak detection and rectification programme', CMWSSB has embarked upon an ambitious plan for reducing the leakage in the distribution system which, according to an estimate, was to the order of about 23%. In the initial phases of its implementation, it was found that bulk of the systemic losses were mainly on three points:-

      1. Leaky and damaged distribution mains;
      2. Ferrule Points; and
      3. House service connections.
2.2.2. Under recently concluded third phase of implementation of this programme, which covered around 36,900 house service connections, these findings were further validated. In the current on-going programme costing about Rs.160.00 Crores which is to cover nearly 2.60 lakh house service connections, therefore, it has been decided to:-
      1. Replace all the leaky and damaged distribution mains;
      2. Replace all the PVC and AC mains, since over 95% of these are found to be damaged;
      3. Re-fix ferrule on all the connection points; and change all house service connections, which were historically made up of GI Pipes with MDPE corrosion resistant pipes.
As of now, nearly 1,24,000 house service connections have been replaced. The remaining works would also be completed before 2001. A quick survey and evaluation of the implementation of this programme has confirmed that due to these leak detection and rectification works not only the quantities or availability of water has increased and the percentage of leak levels have come down to about 5% from the earlier 23%, the quality of water supplied has also improved greatly.

2.3. RAIN WATER HARVESTING

2.3.1. Rainfalls are the major source of water in a place similar to Chennai City environment where no perennial rivers flow. Moreover, Chennai is prone to get maximum rainfall only during two months ie. October and November in a calendar year. During this period, therefore, a large amount of precious water flows into sea as floodwaters. We believe that converting this flow to potential use can successfully be done by Rainwater Harvesting techniques. Right from early nineties, therefore CMWSSB has been vigorously advocating the"Rainwater Harvesting" and also has developed several type-designs to suit the individual properties/flats. CMWSSB is, perhaps, the first water utility in the country to have made it mandatory to provide rainwater-harvesting facilities in the newly developed properties within the city. In coordination with the regulatory authorities such as Chennai Metropolitan Development Authority and Chennai Municipal Corporation, CMWSSB has made it compulsory during 1994 itself for the property developers of multi storied and special buildings to install suitable Rainwater Harvesting facilities, without which planning permissions will not be accorded. From the current year this has been extended to even individual households (single storied) for which planning permissions are sought. CMWSSB before providing House service water/sewer connections ensure that these mechanisms have been put in place.

2.3.2. During the year under report, the Board, in collaboration and consultation with leading NGO's, Voluntary Groups and Consumers' Associations, and other Government Departments and institutions has embarked upon a renewed and an intensified campaign to propagate the "Rainwater Harvesting Methods". Free training programmes on "Rainwater Harvesting" are being conducted on all the working days at Metrowater Training Centre. These training programmes, widely publicized through the local newspapers, have evoked tremendous response and an entire spectrum of the public - individual households, property developers, engineers, consultants, residents associations, housewives, students and other professionals have been attending. Some of the participants are also from out side the Chennai City. A shortlist of Contractors who will be able to take up thc construction of Rainwater Harvesting structures at fixed rates has been prepared and published to enable the public to use their services. With a view to ensure a clearly focused effort, a special purpose vehicle - "Rainwater Harvesting Cell'' has been constituted in CMWSSB and services of a team of technical personnel have been made available for providing guidance and assistance to the public on Rainwater Harvesting measures. A study was also carried out in one of the areas where rainwater harvesting has been implemented by the residents.

2.4. CONTROL AND REGULATION OF EXTRACTION OF GROUND WATER

Tamil Nadu Government is next only to Gujarat to enact a Ground Water Regulation Act as early as 1987. Faced with rapid depletion of ground water storage and fall in the water table in and around Chennai City and intrusion of sea water in some locations affecting the water quality, the Ground Water Regulation Act was enacted in the year 1987. The location of surface storage lakes and main groundwater aquifers along with the area of operation of the Ground Water Regulation Act are shown in the source map at inside cover page. (page ) This Act aims at controlling and regulating the extraction of ground water so as to conserve the otherwise delicate and fragile aquifer and save it from sea water intrusion. Under the Act CMWSSB has been vested with the authority to regulate the extraction of ground water in the notified area by a licensing mechanism, which in the city it handles directly. In the areas outside city limits, however, the revenue authorities of the respective area have been permitted to issue licenses to extract and transport ground water based on the recommendations of CMWSSB. No new permits for extraction of ground water or its transportation have been issued since 1997 nor the licenses already granted have been renewed inspite of the substantial revenue receivable on the license fee. Due to strict enforcement of the act during the last l2 to13 years or so the water table with in the city and adjoining Southern Coastal Aquifers has increased greatly as shown below. As the penal provisions for the violations in the Act are minimal, now proposals have been formulated for amending such provisions to invoke heavier punishments.

P.S : The fall during 1998-99 is attributable to extremely low rainfall

2.5. RECHARGING OF GROUND WATER

Ground water sources to a large extent next to surface water (obtained from the three reservoirs feeding the City) are crucial to CMWSSB. While surface water depends upon the monsoon rain and river sources, ground water availability as discussed earlier in this report also depends upon the level of extraction. It so happens that the Board has to heavily depend on this source consequent upon inadequate rainfall once in three-four years. Therefore for our situation, conservation of ground water source has become a must. In order to enable fast recharging of the aquifers during monsoon, three check dams were constructed during 1991 across river Korataliyar. The effect of these checkdams has been quickly visible as seen from the gradual rise in the water table .

2.6. RE-USE OF SECONDARY TREATED SEWAGE FOR INDUSTRIAL PURPOSES.

Another concept by which conservation of fresh water has been attempted is re-use of secondary treated sewage for industrial purposes. To achieve this, two major water-intensive industries, (an oil refinery and a fertilizer plant) were advised to use the secondary sewage effluent after appropriate further treatment. They have set up tertiary treatment units and about 50 MLD of secondary sewage effluent is, supplied by CMWSSB for industrial use. This practice of reuse of water has been taken up further by a power plant which came into existence about a year ago and on our advice, has started using about 10 MLD of raw sewage after further treatment at their premises. However, to make any significant impact the concept has to be pursued further.

3. MAJOR PLANS FOR THE FUTURE:

    1. UPGRADING AND PROTECTING THE ENVIRONMENT BY

    2. IMPROVING THE QUALITY OF CITY WATER WAYS:
      1. Cooum and Adyar rivers flow through the city, with a man-made Buckhingam canal linking these two rivers. Essentially these waterways were functioning as flood carriers and have flows only for about two months in a year during monsoon. Flow in these watercourses in the rest of the year is mainly due to discharge of treated, partially treated and untreated sewage through about 311 No. of outfalls meant for storm water discharge resulting in accumulation of large volumes of sludge and silt, formation of sand bar in the mouth of rivers and prevention of free discharge into sea resulting in stagnation of waste water in water courses. This has also created significant problems as to the flood protection system, storm water drainage network and associated public health resulting in overall degradation of city environment. Our long term objective in the handling of wastewater therefore, nonetheless is both to prevent noxious substances from reaching the wastewater and to utilise the useful substances available and return them to the environment.
3.1.2. The Sewerage systems in Chennai City as already mentioned, installed in early 1891 were improved and expanded during the past 108 years with different technologies. These gave room for many inadequacies and bottlenecks such as inadequate links in the system, disruption of continuous functioning of sewage treatment plants due to heavy settling of silt in sewage, inability to operate sewage pumping stations continuously etc, which further resulted in surcharging of sewers, settling of silt and consequent sewage over flows reaching the water ways over several years directly.

3.1.3. In 1989-1996, Metrowater availed of the assistance provided by Government of Tamil Nadu through a British consultant carried out several works and removed many of the above constraints in the sewerage system. Sewers are now being desilted using machineries and operation of sewage pumping stations has also considerably improved. Because of these operational improvements individual complaints have generally reduced to almost 50% level. Further ongoing improvement works in the existing sewage treatment plants at Kodungaiyur, Koyambedu, Nesapakkam and Villivakkam at a cost of Rs.51.00 crores with loan assistance from HUDCO and TUFIDCO are likely to sustain the gains further. However, consequent on receipt of Krishna Water and upon almost doubling the quantity of water supplied, the capacity of existing sewerage systems has become grossly inadequate and needed major improvements if the discharge of untreated or partially treated sewage into city water ways had to be prevented.

      1. It is estimated that totally about Rs.1300.00 crores may be required to complete all the works necessary to upgrade and maintain the overall city environment. As this cost is phenomenal and beyond the reach of Metrowater, it has been proposed to implement the works in two stages synchronising with the progressive water supply augmentation plans. Hence in the first stage it is proposed to improve the capacity of those components in the sewerage system which are currently inadequate to handle the sewage flows expected consequent upon supply of 627 mld of water to materialise within next few years. In the second stage further improvements as to the remaining works are proposed to be taken up after 2005.
3.2. CHENNAI CITY RIVER CONSERVATION PROJECT

3.2.1. As stated in preceding paragraphs CMWSSB has conceived a comprehensive project for 'Interception, Diversion and Treatment of sewage' under the umbrella " Chennai City Rivers Conservation project" costing about Rs.615.40 crores for carrying out the following works and has posed for financial Assistance to the Government of India, Ministry of Environment and Forest under the National River Conservation Directorate.
 
 
 
 
 
 
Component
Quantity
Cost Rupees in Crore
1 Laying interceptors and capacity expansion. 65.22 km.
159.30
2 Capacity enhancement of Pumping Stations & Pumping mains to ensure diversion of sewage to treatment plants, and a) 33 no.of Sew.PSs
133.20
  b) 50.02 km. Pumping mains.
156.90
3 Expansion of capacity of treatment in four sewage treatment plants and installing treatment for bacterial reduction in all six sewage treatment plants Expansion of capacity

Bacterial Reduction

264 mld

627 mld

166.00
 
Total
   
615.40

As explained earlier, this Project has been posed to the National River Conservation Directorate, Ministry of Environment and Forest, Government of India for funding, approval for which is expected during the year 2000-2001. Chennai Metrowater is in readiness to take up the works for implementation and completion during next 3 to 4 years. These works once, completed would greatly improve the quality of the watercourses in Chennai City.

 SIGNIFICANT ACHIEVEMENTS DURING 1999-2000

REPORT BY MANAGING DIRECTOR

Chennai Metropolitan water Supply and sewerage Board, at present serves a population of about 60 lakhs mostly within the Chennai Municipal Corporation area.

1. ORGANISATIONAL GROWTH AND DELIVERY OF SERVICES:

It has been the continued objective of Chennai Metropolitan Water Supply and Sewerage Board to make significant strides in the quantity and quality of water supplied, population covered, to adopt more efficient means of sewerage collection, interception, transmission, treatment and disposal and to serve its consumers in the best possible manner. Chennai Metropolitan Water Supply and Sewerage Board, in the last 22 years of its existence, has attained considerable progress in this regard. Some of the significant achievements made in the year 1999-2000 are presented below:

  1. WATER SUPPLY TO CHENNAI CITY

  2. 2.1. WATER SUPPLY SOURCE AUGMENRATION AND MANAGEMENT:

    2.1.1. The main sources of water supply to Chennai City are twofold:- (1) Surface water (rain and river water) stored in Poondi, Cholavaram and Redhills lakes, with the total capacity being 7412 mcft; and (2) The ground water sources that include Poondi, Tamaraipakkam, Flood Plains, Kannigaiper, Panjetty and Minjur aquifers consisting of deep bore wells. Besides this, small quantity of water drawn from Southern Coastal Aquifer and Infiltration Wells from Porur Lake is also utilized.

    2.1.2. With the water sources mentioned above, the rate of water supply in the city was maintained at 70 litres per capita per day (lpcd) totaling about 290 Million Litres per day upto the period prior to September 1996. After receipt of Krishna water as an additional source from October 1996 onwards, however, the water supply was enhanced to an average level of 100 lpcd thus increasing the total water supply to 480 ML daily.

    2.1.3 The water storage position in the lakes and the status of water supply to the city were reviewed regularly, the quantity of water supply decided and the situation managed. Especially every year, at the end of North East monsoon (i.e.) as on 1st December, the storage position in the lakes would be taken into account and accordingly the quantity of water to be supplied during the next year regulated.

  3. RAIN FALL AND THE STORAGE POSITION IN THE LAKES:
    1. The annual average rainfall in the catchment areas of the lakes – Poondi, Cholavaram and Redhills is about 1300 mm. During 1999, however, the rainfall was only 607 mm which was the lowest during the last two decades .
  4. SITUATION MANAGEMENT:
4.1. As already mentioned in the report elsewhere, the combined storage in the three reservoirs as on 1 st December 1999 was just 2114 mcft. This situation could not be averted due to extremely poor rainfall in the catchment as also lesser receipt of water from the Krishna source. To mitigate this scarcity situation, therefore, what we were left with was to ensure an "efficient management and distribution", by
    1. Identification of additional sources of water and efficient monitoring and management thereof; and
    2. Properly regulating the distribution.
  1. IDENTIFICATION OF ADDITIONAL SOURCES OF WATER:

  2. 5.1. In view of the above scarcity situation though the Government of Tamil Nadu were persuaded to permit the Board to use the available water from a nearby irrigation tank Chembarambakkam for drinking water purposes, the problem was the non-availability of a proper ‘water transfer system’. Therefore, in order to convey the available water i.e. about 1100 mcft from Chembarambakkam Lake for the City supply an open surplus channel called Thanthi Canal was identified and water transported to Porur lake situated at about 11 Kms distance, and from this point onwards about 75 to 100 MLD of water was pumped by installing three 250 HP Pumpsets at Porur lake bund, through an existing 1200 mm dia PSC clear water transmission pipe line backward and in the reverse direction to the conduit at Redhills for onward transmission to Kilpauk Water Works for treatment and supply to the city. This was the first time that such a large quantity of water has been utilized for drinking purposes from Chembarambakkam Lake and also it was for the first time that the Board experimented and succeeded in transferring such huge quantities of water through reverse pumping method.

    5.2. From December 1999 to June 2000, about 18 Million Litres per day of water was also drawn and supplied from another local source known Rettai Eri near Kolathur.

    5.3. So also from Panjetty, Minjur, Tamaraipakkam and Poondi Well Field Sources from where during previous years only about 40 to 45 MLD of water was extracted from 33 bore wells and supplied to the commercial consumers in and around Manali area, from December 1999 onwards, about 95-100 Mld of water was extracted thus enhancing the city supply by about 50 MLD. This could be achieved by rejuvenating 13 old and defunct wells and also by erecting 28 new deep borewells in a record time.

    5.4. Further, from several local wells within Chennai City about one MLD of water was drawn and put to the City supply system.

  3. CLOSE AND CAREFUL MONITORING OF WATER SOURCES AND EFFICIENT MANAGEMENT:
Lower rainfalls in the catchment areas of the three lakes feeding Chennai City coupled with the low rainfall in the southern parts of Andhra Pradesh gave a few anxious moments to Metrowater as to the prospects of maintaining adequate water supply to the City. Although, all available local sources were consolidated and abstraction from the well fields was also increased to mitigate the situation, it was by close and constant review and monitoring of the source and storage position in the lakes and by adopting some of the most efficient and best distribution practices, the Board could continue to maintain daily supply of water @ 250 ML per day. When compared to drought situations in earlier years, this quantity was the highest. Some of the salient features are illustrated below:

6.1. The brightest spot in this scarcity situation, however remained the maintenance of daily water supply at reasonably good level. Unlike in the previous similar situations, the Board in the year under report did not resort to alternative day supply. Obviously, this not only indicated better 'benchmark' of Metrowater’s performance when compared to previous drought situations; but also gave us enough confidence to manage such situations in future in much better manner.

    1. In the year 1983 - a drought year, from March 1983 to October 1983, we could maintain only an alternate day supply at the rate of 220 ML which is equal to the daily supply of 110 MLD.
    2. During June 1987 to November 1990 - another long spell of drought - alternate day supply was resorted to and that too at the rate of 180 ML which is equal to the supply of mere 90 MLD.
    3. So also from January 1993 to March 1994 again only alternate day supply could be maintained and that too the quantity supplied varied between 227 ML to 65 ML, working out to an average supply level of 113.5 MLD at the beginning of drought period which ultimately went down to the level of mere 32.5 MLD at the end of drought.
    4. Status of water supply during various drought periods is graphically presented below.


Water supply during drought periods

  1. MOBILE WATER SUPPLY:
7.1. During the later part of the year under report, as already mentioned, due to the drought situation, the Board could maintain piped supply for about 70% (45 lakhs) of the population at the rate of about 55-60 lpcd. For the remaining 30% (16 lakhs) of population, water supply had to be provided as a purely adhoc and temporary measure by installing about 5500 numbers of stationary tanks and also through mobile supply by about 3800 lorry trips per day by distributing about 35 mld. of water. Besides this the water quantities were also augmented by renovating the existing 4166 India Mark II pumps and also by putting up about 1050 additional India Mark II pumps which provided not only better access to the safe drinking water for the poor and slum dwellers but also served as fallback arrangement for many throughout the city.

8. WORLD BANK’S PAT FOR METROWATER:

8.1. The efforts taken by the Metrowater in mitigating the water needs of Chennai City with the available source and its ability to maintain satisfactory supply were also commended by the World Bank whose Mission visited Chennai Metrowater during June 2000 for a review of the progress of

on-going Second Chennai Water and Sanitation Project funded by the Bank. The observations of the Bank are reproduced below

" Metrowater has demonstrated better capacity to manage the drought than on previous occasions. In particular, the impact on the progress of physical works has been unnoticeable as opposed to the stoppage of works under the First Project during 1993 drought. A minimal level of service has been maintained through due to improved transmission and distribution systems. GOTN’s decision to use upto 100 MLD from the Chembarambakkam reservoir as a source for water supply; increased availability of water from the aquifers following the approval of the Ground Water Regulation Law and improved management practices. Prior to the receipt of the Krishna water in September 1996, the average daily water supply was maintained at about 290 Mld and after September 1996, the supply level was increased to 480 Mld. In earlier drought periods during 1987, 1988, 1989, 1990 and 1993 water was supplied only alternate days and the quantity varied from 65-227 Mld. This year, daily supply was maintained at an average of about 250 Mld, despite a substantial growth in the number of consumers." * * * * * * "In addition, during earlier drought years, the non-domestic supply was reduced to about 25-32 Mld, whereas this year there has been no significant decrease in supply to industrial and commercial consumers, which explains the limited negative irnpact of the drought on Metrowater's financial position in FY 1999-2000. The anticipated additional expenditure directly related to the drought is estimated at about Rs. 184 million and will be met by Metrowater's own resources as compared to 1993 when Metrowater's expenditures were substantially higher (Rs 489 million) and were financed by a Government grant." * * * * * * "The mission team commended Metrowater for its improved management of the drought and its increased emphasis on proactive measures (such as the creation of a Drought Fund) to manage an event that is recognised as a regular occurrence in Chennai. The team recommended Metrowater to continue exploring options to improve its drought management practices (by possibly storing water in the aquifers during the years of normal rains; improving the water pricing policies to promote water conservation; increasing low-cost water reuse etc.) 8.2. One of the most important and notable feature of this year's drought management has been the demonstration by the Board of its increased capacity and inner strength to fully absorb the shocks without actually affecting its normal activities. Even though the Board had to incur significantly additional expenditures on account of various mitigation works and measures leading to extra attention by men and machinery towards "water management in a scarce situation" like this, progress of construction works and other normal activities of the Board continued at the usual pace. More importantly as observed by the World Bank, this was possible only due to better and efficient management practices adopted as to the managing the water sources, regulating, distributing and maintaining the operations at maximum efficiency.

9. PROGRESS OF PROJECT WORKS:

As stated above, the execution of project and capital works did not lag behind. In fact, not only the Tempo was maintained but also the physical and financial achievements on capital works during the year under report were significantly higher as could be seen from the chart below:

Some of the significant achievements during the year are listed below.

9.1. WATER SUPPLY:

New Water Distribution Stations: Two New Water Distribution stations namely, Valluvarkottam and Triplicane were commissioned during 1998-99. Works on two other water distribution stations namely Kannappar Thidal and Ekkauttuthangal were completed in 1999-2000 and commissioned. Five more water distribution stations at Choolaimedu, Patel Nagar, Kolathur, Mylapore, and Nandanam have been physically completed but could not be commissioned due to the prevailing water scarcity situation. Details of progress/ achievement in this regard are as given below:
Name of the zone
Estimated population to be benefited 

(2021)

In lakhs

Beneficiary Areas
Estimated cost of the work (Rs. in Crores)
Stage of Progress
Choolai-medu
9.68
Aminjikarai (South)

Vadapalani

Saligramam

Kamaraj Nagar, Virugambakkam

and MGR Nagar

22.50
Work completed. To be commissioned in January 2001 after current water scarcity is over
Patel Nagar
2.16
Radhakrishnan Nagar

Cherian Nagar

Tondiarpet 

and Korukkupet

11.35
Work completed. To be commissioned in January 2001. after current water scarcity is over

 

Kolathur
3.89
Kolathur

Villivakkam (North)

Agaram

and Sembium

12.64
98% Work completed. Proposed to be commissioned in January 2001 after current water scarcity is over
Mylapore- Nandanam
4.34 +

2.32

Mylapore

Santhome

Azad Nagar

Beemannapet

Alwarpet and

Raja Annamalaipuram

23.55
98% of work completed. To be commissioned in 

January 2001 after current water scarcity is over

Pallipattu
3.46
Adyar

Thiruvanmiyur

Indira Nagar

and Sastri Nagar

10.47
80% of work completed. Target completion Dec.2000 proposed to be commissioned in Dec’2000
Vyasarpadi
4.47
Kodungaiyur

Vyasarpadi

and Perambur

15.76
65% work completed. Scheduled to be completed in April 2001. But actually proposed to be commissioned by Feb. ’2001
Velachery
1.34
Velachery

and Guindy East

7.45
70% of work completed and scheduled to be completed in March 2001. Actually proposed to be commissioned in Jan.2001.

9.1.1. Clear Water Transmission Mains:

9.1.1.1. Out of seven works, one work viz Madhavaram take off to Vysarpadi Water Distribution Station was completed and commissioned. Water supply to M.K.B. Nagar is presently made through this pipeline. Of the remaining six works, four works namely Porur to Kathipara junction, Pallipattu take off to Mylapore-Nandanam Water Distribution Station, K.K.Nagar to Ekkattuthangal Water Distribution Station and Velachery five furlong road junction to Velachery Water Distribution Station though were completed during this year these could not be commissioned due to current water scarcity. These are proposed to be commissioned by Jan.2001 once the present scarcity is over. The progress of the two ongoing works is as follows:-
Sl.

No.

Description of work
Estimate cost (Rupees in crores) Total length of pipe line Length laid so far. Stage of Progress
1. 1300mm dia main from Kathipara to Pallipattu take off point
12.60
5980m
5100m
90 % Work completed. Expected to be commissioned in January 

2001.

2 Branch transmission main from Gangadeeswarar Koil street to Triplicane and Kamarajar Thidal WDS
7.57
5280m
  Work commenced on 15.3.2000. 

 

9.1.2. STRENGTHENING THE LOCAL WATER DISTRIBUTION NETWORK:

The contract for strengthening of local distribution network in 8 Zones namely; Patel Nagar, Vyasarpadi, Kolathur, Choolaimedu, Ekkattuthangal, Kannappar Thidal, Nandanam and Pallipattu were awarded in four packages during May and June 1999 and the works are in progress. Due to totally transparent tendering procedures as also partly due to rupee devaluation since the Board recorded a saving of about Rs.70.00 Crores, (out of the Project Cost for Rs.540.00 crores) World Bank was persuaded to sanction certain additional works. As a result of this, the contracts for 3 more zones viz. Valluvarkottam, Mylapore and Velachery were awarded in Feb’2000. These works are also progressing well as may be seen from the statement below.
 
 
Sl.No. Name of Zone / Package Estimate Value

Rs.in lakhs

Contract Value work awarded Completion date Total length (laying KM) Progress as on 3/2000 (laying Km)
1&2 Choolaimedu & Kannappar Thidal 5914.84 4550.00 21.5.99 20.5.2002 122.73 4.37
3&4 Ekkattuthangal & Patel Nagar 2212.36 1885.00 21.06.99 20.06.2002 70.73 12.75
5&6 Pallipattu & Nandanam 3453.74 2782.00 21.05.99 20.05.2000 94.02 7.70
7&8 Vysarpadi& Kolathur 5530.00 4317.00 21.06.99 20.6.2002 181.98 1.93
9 Valluvar-kottam 1465.70 1071.80 21.2.2000 19.3.2002 Supply of pipes to commence by June 2000.
10 Mylapore 2250.00 1477.80 23.2.2000 08.3.2002 Supply of pipes to commence by June 2000.
11 Velachery 2180.80 1447.80 23.2.2000 26.3.2002 Supply of pipes to commence by August 2000.

9.1.3. EXTENDING THE WATER SUPPLY COVERAGE TO ADJACENT URBANISED AREAS:

9.1.3.1 As already reported during the previous annual report, though, hitherto Chennai Metropolitan Water Supply and Sewerage Board catered to the water supply and sewage disposal needs of Chennai City limits, last year the Board decided to extend the water supply services to certain identified Adjacent Urbanized Areas (AUAs). The Master Plan 1978 has evaluated the demand and allocation of water in the Adjacent Urbanized Areas and Distant Urbanized Areas, for the years 2011 and 2021 as below:-
 

  Water Demand and allocation in Adjacent Urbanized Areas :
 

Sl.

No.

Name of Adjacent

Urbanized Areas

Demand (mld)
Allocation (mld)
2011
2021
Stage-I
Stage-II
1.
Thiruvottiyur
64.70
80.00
20.40
34.20
2.
Madhavaram
45.10
62.80
12.60
24.40
3.
Manali        
4.
Kathivakkam
13.90
15.90
4.40
7.80
5.
Chinnasekkadu
1.90
2.30
0.60
1.00
6.
Alandur
45.50
56.60
14.20
24.30
7.
St.Thomas Mount
19.40
23.90
6.00
10.40
8.
Kottivakkam
1.50
2.00
0.50
0.80
9.
Perungudi
1.60
2.00
0.50
0.90
10.
Pallikaranai
21.60
22.50
5.90
11.50
11.
Puzhuthivakkam
3.30
4.00
1.10
1.70
12.
Nandambakkam
2.90
3.50
1.00
1.50
13.
Ambattur
101.60
118.40
31.10
36.00
14.
Valasarawalkam
3.60
4.60
1.20
1.90
15.
Maduravoil
3.50
4.50
1.20
1.90
16.
Ramapuram
1.70
2.10
0.60
0.90
17.
Nerkundram
2.40
3.10
0.80
1.30
18.
Ayanambakkam
0.90
1.10
0.30
0.50
19.
Porur
4.50
5.90
1.50
2.40
20.
Avadi
81.00
95.70
26.10
31.50
 
TOTAL
420.60
510.90
130.00
194.90
 
         

 

9.1.3.2.. Meanwhile, in order to meet the immediate requirements of a few Municipalities/Town Panchayats in the adjacent urbanised areas separate schemes utilizing the existing infrastructure as also by providing additional infrastructure to the required level were formulated and implemented as below.

    1. For Korattur, which is a part of Ambattur Municipality, works at a cost of Rs.96.01 lakhs were taken up and completed. Presently about 1.5 MLD of water is being supplied.
    2. A Project costing Rs.26.54 crores for upgrading and strengthening the available infrastructure facilities for extending water supply to the following local bodies was taken up and works completed during the year as below:-
Sl.

No.

Name of the 

local body

Qty. of

additional

water

to be

supplied

in mld.

Popula-tion

benefited

in lakhs

Cost

of the

project

(Rs. in

Crores)

Stage of

Project

1. Alandur 12.8 1.50 6.65 All works

completed

2. St.Thomas Mt. 1.6 0.55
3. Pammal 3.0 0.50 3.90 All works

completed

4. Anakaputhur 1.5 0.26
5. Meenambakkam 0.5 0.12
6. Pozhichallur 1.0 0.26 2.86 All works

completed

7. Cowl Bazaar 0.5 0.12
8. Ullagaram &

Puzhuthivakkam

0.8 0.18 2.83 All works completed. Addl. works for Rs.1.65 Crores are also proposed to be taken up.
9. Porur

(a) Head Works

3.2 0.35 1.59 All works completed except one OHT (court stay).
  (b) Distribution

System

    2.67 95% works completed
10. Valasara-

walkam

2.6 0.31 1.85 Work completed
11. Maduravoil 1.9 0.32 2.90 Works completed
12. Ramapuram 2.0 0.31 1.29 Works completed (addl. works for Rs.0.38 Crores are also proposed to be taken up)

TOTAL
0


9.1.3.3. For augmenting water supply from 14 lakh litres to 41 lakh litres to Ambattur Municipality, an improvement scheme comprising UGTs, pump houses and feeder mains at locations Athipet, MTH Road opposite to T.I.Cycles, Venkatapuram, Mannurpet, Korattur and Thathankuppam at a cost of Rs.3.37 Crores has been taken up and works are under progress.

9.1.3.4. In a similar manner for Avadi Municipality to augment supply from 8 lakh litres to 24 lakh litres pipe laying and pump set erection works at a cost of Rs.4.23 crores to benefit Avadi Main Town, Thirumullaivoyal, and Pattabiram parts of Avadi Municipality have been taken up and are under progress.

9.1.3.5. A scheme for providing water to Pukhraj Nagar portion of Madhavaram Municipality costing Rs.0.94 crores was completed and put to use. Further, another scheme for water supply to Thanikachalam Nagar part of Madhavaram Municipality at an estimated cost of Rs.2.4 Crores has been formulated and is at design stage.

9.1.3.6. Above stated works are for catering to the immediate requirements. Towards long term solution to provide water supply to all the 20 AUAs for (i) preparation of master plan, (ii) detailed engineering; and (iii) bid documents; it is proposed to hire a consultant and complete the work by obtaining financial assistance from the World Bank through Tamil Nadu Urban Development Fund. The work is proposed to be completed in about two years period.

9.2. SEWERAGE

9.2.1. Expansion of sewage facilities to unsewered areas: In furtherence to the declared policy of providing sewerage to unsewered areas, works for providing sewerage systems in Kanagam-Taramani, Kodungaiyur (North & South) Vyasarpadi Lake area, Velachery, Sarathy Nagar and Dr. Radhakrishnan Nagar (North & South) were completed. These include construction of 14 pumping stations and laying of 138.18 km of pumping main and force mains besides providing Collection System to a length of 117.09 km and house service connections.

9.2.2. Rerouting and replacing of sewers : Rerouting of 600mm dia CI force main from Law College pumping station to Royapuram pumping station costing Rs.18.76 Lakhs has been taken up and the work is expected to be completed shortly.

9.2.3. Providing intercepting sewers along Mambalam canal: To improve the quality of city water ways, works for providing interceptors along the waterways to intercept untreated sewage flowing along the Mambalam canal and put the collected sewage back into the system at a cost of Rs.9.00 crores have been taken up on experimental basis. This is programmed to be completed by Nov 2000. Once this experiment has been found to be successful, it would be extended to other areas also.

9.2.4. Improvement to 16 sewage pumping stations : Comprehensive improvement works in 16 major pumping stations have been taken up and completed in 11 pumping stations. Remaining works on 5 pumping stations are also expected to be completed shortly.

9.2.5 JBIC assisted sewage renovation and functional improvement project

Under this project, two contracts, - one for the Effluent conveyance system costing Rs.33.65 crores for conveying raw sewage from Koyambedu - Villivakkam to Kodungaiyur and the other for conveyance of treated water from Kodungaiyur to Manali industrial consumers costing Rs.36.34 crores were finalised and works awarded. These are expected to be completed by March 2001.

9.2.6 Providing sewerage to economically weaker sections:

In addition to the above, top priority, has been given to provide sewers in Adhi Andhra habitations and Colonies in low lying areas primarily inhabited by economically weaker sections. 24 km. of sewers and force mains were laid and 4 no. of pumping stations constructed and the systems commissioned benefitting a total population of about 25,000.

9.2.7. Improvement to existing Sewage Treatment Plants: With a view to sustain the quality oftreated sewage, certain immediate improvement works in five sewage treatment plants at Kodungaiyur Zone-I & II, Koyambedu, Nesapakkam and Villivakkam costing about Rs.51.00 crores have been initiated. These works are likely to be completed by end of 2001.

10. OPERATION AND MAINTENANCE - A PARADIGM SHIFT

10.1. The gains secured consequent upon conceptual switch over from the 'breakdown maintenance' to that of 'preventive maintenance'. were further strengthened during the year under report. This vital decision of the Board recognising and institutionalising the concept of "preventive maintenance" as also putting in place necessary supporting systems has transformed the entire arena of operation and maintenance activities. Some of the significant initiatives are detailed below:-

    1. Systems of annual rate contracts for the procurement of materials and standard works-contracts initiated a few years ago were further strengthened. Standardization of these procedures has resulted in substantial cost savings as also increased efficiency and productivity.
10.3. BUILDING LONG RANGE PARTNERSHIP WITH PRIVATE SECTOR: Private sector participation in water and sewerage sector is another aspect upon which the Board has been focussing its attention quite systematically. The Board has already involved the private sector by entrusting the operation and maintenance of a water treatment plant, water production wells and several sewage pumping stations. Board's experience of working with the private sector revealed that good and proper understanding of risks by private sector partners and also by water authorities was absolutely essential for the success of privatisation efforts. There is also a need for Nationwide debate on the accountability of the private sector operators undertaking the ‘public functions’ which historically have been the Government’s Domain so that the accountability of the Government is also assured besides protecting the citizens' rights'.

10.4. Board also envisages private Sector participation as a part of its ‘market oriented financial systems-package’ and also as ‘ alternative systems of management’ towards securing increased efficiently and cost –effectiveness. The initiatives taken by the Board in this direction during the previous years were therefore, pursued further. Besides continuing with the private sector partnership in the management of some of the smaller and isolated engineering operations, during the current year, the CMWSS Board also opened up many core and service sectors, like accounting and financial management functions to the private sector. The experience of working together with the private partner has benefited CMWSS Board in not only obtaining increased efficiency but also substantial cost savings. Cases of cost savings are indicated below:

Areas of privatisation
Annual Savings
in percentage Rupees in lakh
Operation and Maintenance of Well Fields 56% 14.60
Water transport through private lorries 18.5% 138.40
Maintenance of Sewage pumping Stations 65% 32.14
Maintenance of Sewerage treatment plant 33% 4.67
Maintenance of Water treatment plant (+)14.4% 90.90

(Excess)

Head Works 46% 14.00
Chlorination Plant inside KPS 32% 1.56
Security 10.42% 4.18

10.5. MANUFACTURING BOTTLED ULTRA PURE DRINKING WATER:

10.5.1. Driven by quality and cost consideration as also to cater to the needs of the upper income groups and that of large travelling population, Metrowater had been contemplating production and supply of bottled -Ultra pure water at most affordable cost. Finding it a feasible proposition, Metrowater thought of inviting private entrepreneurs, who could install the required machinery, produce and market bottled drinking water.

10.5.2. Duly applying the laid down procedures therefor, M/s. Emperor Aqua Limited – a private company has been authorised to produce and market packaged ultra pure drinking water (mineral water) under a joint venture licensing agreement. For this purpose, 15,017.65 sq.ft, of Metrowater’s vacant land has been allotted to the firm at Metrowater Resource Centre in Kilpauk Water Works Complex. The firm constructed the plant and installed required equipment as their own share in the venture and commenced production on 09-12-1999 Under the agreed working arrangement, whereas the production, supply and marketing etc. are the responsibility of the private sector partner, the responsibility to ensuring quality and maintaining affordability lies on the Metrowater.

10.6. Private Sector Participation – Lessons Learned and some Legal

Issues

10.6.1. Some of the important lessons learnt by the Board in this area are

summarised below:

      1. However, some of the legal issues engulfing the private sector participation as we have seen are:-
    1. Private Sector’s responsibility for legal suits/penalties levied by the Government or any regulatory agency in case of harm that may be caused to environment or living beings is very much lacking and needed to be settled.
    2. Adequate legal provision for compensation for losses due to lesser output are lacking.
    3. Adequate legal frame work for compensation for losses due to improper quality and if the obligations not met by private operator in respect of labour related issues such as concerning accidents, child labour, Mimimum Wages Act etc.
10.6.3. Private Sector Participation – The Future Agenda

Enriched with the experiences gained and having got a fair knowledge of the issues arising with the private sector participation in water and sanitation sector, the Board has drawn up its future agenda as below:

11. FINANCE

11.1. FINANCIAL RESULTS

The Structural and financial reforms implemented during the year under report and the analysis, review and control of operating expenditures and debt service charges helped the Board to end the current year with a definitive - positive note. The Board continued to record net operating income this year also, which is the eighth successive year showing operating surplus. The total income during the year has been to the order of Rs. 207.01 crores and the total expenditure Rs.181.51 crores, thus recording a net surplus of Rs. 25.50 crores. Achieving of this net surplus during the year under report has been further more significant due to the fact that during the fag end of the fiscal year, the Board had to substantially reduce the quantum of water supplied due to failure of monsoon on one hand and on the other side it had to incur additional expenses in maintaining the supply line and managing the drought. Of the revenue income whereas the greater share is attributable to water charges as in the previous year, the employee cost remained one of the larger components of revenue expenditure. Although this is one area of greater concern to the financial managers, the Board continues to accord high priority to employee's welfare.


 
 
 
 

11.2. FINANCIAL REFORMS.

11.2.1. INTRODUCTION OF MANAGEMENT AUDIT:

Reforms initiatives in the Financial Sector continued to be pursued during this year also. In order to further strengthen the financial systems of the Board and to improve the quality of reporting covering physical aspects of operation and maintenance the Board introduce the concept of ‘Management Audit’. While creating suitable structures for the "management audit functions", the Board made this as integral part of overall financial systems with well-defined responsibility of the audit wing. Various concepts such as transaction audit, compliance audit of Government rules and procedures, system's audit, management audit, energy audit, store's audit etc, have been clearly defined and used as tools to enhance productivity. To carry out these audit functions, the Board approved the appointment of a Controller of Finance (Internal Audit II) in Grade III with the qualification of Chartered Accountancy or Cost Accountancy. To assist him in his functions, a Deputy Controller of Finance (IA-II) with Chartered Accountancy qualification was also appointed. One of the objectives of the management audit wing is also to implement the Cost Oriented Savings Oriented (COSO) techniques in its audit functions.

11.2.2. WIDENING FUND MANAGEMENT CONCEPT

Taking care of future obligations is another vital function of any financial management. Towards this end, the ‘Fund Management concept’ introduced in the previous year was widened and persued further. The year saw in creation of a contingency or ‘Drought Management Fund’ besides making contributions to Depreciation, Repairs and Renewals, Pension Fund, etc., which were created during the previous year, thereby recognising the fact that contributions from the years of net income will have to be made for taking care of future obligat